Internal Audit - Progress Report 2012 / 13
Date: March 2013 Contents
Introduction 1
Key Messages 1
Internal Audit work completed from 01/04/12 to 22/02/13 1
Other Significant Work 2
Audits in Progress 2
Performance Information 2
Other matters of Interest 3
Appendices Appendix 1 – Assurance Definitions 6 Appendix 2 - Outstanding recommendations as at 22/02/13 5 Appendix 3 – Internal Audit Plan & Schedule 2012/13 4
Contact Details: Lucy Pledge CMIIA Head of Audit & Risk Management
County Offices, Newland, Lincoln, LN1 1YG : 01522 553692 [email protected] Audit Lincolnshire – Internal Audit Progress Report
Introduction 1 The purpose of this report is to: Advise of progress being made with the Audit Plan Provide details of the audit work during the period Provide details of the current position with agreed management actions in respect of previously issued reports Raise any other matters that may be relevant to the Audit Committee role
Key Messages
2 Work towards delivery of the 2012/13 audit plan is progressing well. The majority of the finance audits are now underway – this has enabled transaction testing to be undertaken across the majority of the financial year. The schedule of audits is on track and we anticipate that the plan will be 100% complete by the end of the year.
Internal Audit work completed from 01/01/13 to 22/02/13 3 The following audit work has been completed and a final report issued:
Full Assurance Substantial Limited No Assurance Assurance Assurance
Value for Money
Note The Audit Committee should note that the assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. Definitions levels are shown in Appendix 1.
4 Progress with the implementation of agreed management action on recommendations for audits resulting in ‘No’ or ‘Limited’ assurance is followed up and reported in Appendix 3. Overall, implementation of recommendations is progressing well. Some revised dates have been provided by managers, and we will continue to monitor actions being taken.
5 In the audit given Substantial Assurance, we confirmed that the Council has sound processes in place:
Value for money – the council continues to work closely with Procurement Lincolnshire to secure value for money in large value contracts, and
Page 1 of 11 Audit Lincolnshire – Internal Audit Progress Report
officers have good awareness of the need to obtain value for money and follow contract regulations. A review of the contract register identified that some details need updating, which will be done as part of the implementation of Procurement Lincolnshire’s new contract register software (Firefly)
Other Significant Work 7 Other work undertaken includes:
Combined Assurance Model The combined assurance report has now been finalised and is being presented to this Committee under a separate agenda item.
Draft Plan 2013/14 We have drafted the audit plan for the next financial year, and this is also being presented to the Committee today.
Audits in Progress 8 The following 2012/13 audits are currently in progress: • NNDR – fieldwork complete • Housing Benefits (including welfare reform) – fieldwork commenced • Project Management – draft report • Risk Management – draft report • Creditors – scoping agreed • Capital Accounting and Asset Control – draft report • Accountancy – draft report • Section 106/Planning Obligations – scoping agreed • ICT follow up – draft report
Performance Information 9 Our current performance against targets is shown below:
Performance Indicator Target Actual @ 22/02/2013 Percentage of plan completed. 100% 80% (revised plan) Percentage of key financial systems 100% 72% completed. Percentage of recommendations 100% 100% agreed. Percentage of recommendations 100% or escalated 64%
Page 2 of 11 Audit Lincolnshire – Internal Audit Progress Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2: Internal Audit progress Report March 2013Report | 679 KB | DownloadRead as text |
PDF |
Internal Audit Progress to March 2013Report | 78 KB | Download |
Follow Audit Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | Follow Up ItemsThat the Follow-Up Items report be noted. | Noted | Open |
| 20 Jul 2026 | Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... | Approved | Open |
| 20 Jul 2026 | Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. | Noted | Open |
| 20 Jul 2026 | Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.