Half Year Financial Performance 2013/14

Approved Executive 6 papers

Executive Board approved this item on Thursday 7 November 2013. Below is the council's own wording, with the papers it was decided on.

Item78

Resolved

Approved: 1. The noting of the financial position on the Council’s General Fund, HRA Revenue account and Capital Programme. 2. The establishment of an Apprentice reserve from the underspend in the 2013/14 to cover the cost of the programme over 2014/15 and 2015/16. 3. An £85,600 increase in the budget for the Sleaford Leisure Centre Refurbishment to be met from external grant receipts. 4. A £15,300 increase in the budget for the acquisition of the Southern Sleaford Development Site. 5. An increase in the budget for the New build scheme at Princess Margaret Avenue, Metheringham from £320,000 to £381,100. 6. An increase in the budget for the New build scheme at School Lane, Helpringham from £518,000 to £588,800. 7. Purchase and funding for £14,200 in respect of the HRA Handy Man Van from the HRA Major Repairs Reserve. 8. The transfer of £150,000 Regeneration funding from the Capital Programme to the General Fund Revenue Programme.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board, 6 pages

Purpose of the report

To report to Executive Board the financial performance and projected outturn for the half year to 30th September 2013. Following reductions in Government funding the Council established a balanced budget through a package of savings and prudent budgeting. To maintain reserves at an appropriate level this report is intended to ensure corrective action can be taken at its earliest opportunity on variances forecast, thus managing the financial risks.

This report will support the Council’s internal control systems, thus providing support to the financial resilience criteria of the Value for Money Conclusion.

2. PROJECTED OUTTURN FOR 2013/14 - Half Year

The General Fund Summary is attached at Appendix 1 and forecasts a surplus of £22,300. It is common at this stage for the negative budget issues to be raised by budget managers while under-spends slowly materialise during the second half of the year. Significant variances experienced for the year are highlighted in the detail below, in section 4.

A grant to compensate the Council for the loss of business rates income as a result of the Governments extension to the Small Business Rate Relief scheme is now expected for 2013/14. To date, no details have been released by the Department for Communities and Local Government on how this is to occur or an announcement on the size of grant they intend to issue to councils. Therefore, it is difficult at this stage to estimate the likely grant award that the Council will receive.

3. FEES AND CHARGES INCOME AND OTHER GRANT INCOME

The Council has five major income streams, derived through fees and charges, which were agreed for the 2013/14 financial year. The table below provides for the progress to date in delivering against the financial targets agreed.

Income Budget Profile as Actual Projected Variance 30.09.13 30.09.13 Outturn (£) (£) (£) (£) (£) Land Charges 130,000 66,300 74,104 141,000 (11,000) Investment Income 259,800 127,543 158,129 307,400 (47,600) Planning Fees 540,000 271,050 493,771 740,000 (200,000) Building Control 239,800 125,986 139,458 239,800 - Car Park 258,800 128,622 140,509 272,200 (13,400) Total 1,428,400 719,501 1,005,971 1,700,400 (272,000)

Planning Fees actual income appears to be on course to be higher than the projected outturn, however, based on the income received during October and the views of Development Management on the anticipated applications due for the remainder of the year the projected outturn remains the same as at quarter 1.

4. SIGNIFICANT VARIANCES

The table below highlights the significant variances (over £10,000).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund Summary 30 09Appendix 1 1 pages Download
PDF
Reserves 2013-14Appendix 2 1 pages Download
PDF
Capital Programme Summary as at September 2013Appendix 3 2 pages Download
PDF
HRA Summary September'13Appendix 4 1 pages Download
PDF
Full Report Half Year Financial Performance 2013-14Report 6 pages DownloadRead as text
PDF
Half Year Financial Performance 2013/14Report 3 pages Download

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Half Year Financial Performance 2013/14This decision
  2. Financial Performance 2020/21 as at 30th September 2020 (Half Year / period 6)Agreed
  3. Half Year Financial Performance 2012/13Approved
  4. Half Year Financial Performance 2011/12Noted
  5. Financial Performance 2010/11 - Half Year ReviewNoted
  6. Financial Performance 2009/10 Half Year ReviewNoted

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies