CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Kesteven District Council
Executive Board, Monday 20 January 2014 at 10.00am

Empty Property Project Officer

Approved Executive 1 paper

Executive Board approved this item on Monday 20 January 2014. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

Approved: That the Empty Property Project Officer post is included in the base budget from 1 st April 2014 as a 0.5 FTE post at a cost of £20,000. Actions: Karen Bradford Stephen Priestly
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Committee: Executive Board Meeting Date: 20 January 2014 Report presented by: Corporate Director Author: Housing Strategy and Growth Manager Email: Stephen_priestley [email protected] Tel: 01529 308295 30829

Report Title: Empty Property Project Officer Post Key Decision Yes No Recommendation to Council Yes No Council Meeting Date: Is this report exempt or confidential Yes No

Purpose of Report To request that the Empty Property Project Officer post is included in the base budget from 1st April 2014 as a 0.5 FTE post

1.0Introduction

CMT will be aware that the Council is currently joint funding the Empty Property project with the funding for the project is due to expire on March 31st 2014. City of Lincoln Council and that funding

The empty property project works to bring longer term empty properties back into use, using a variety of methods including:--

• providing advice and assistance to empty property owners ; • undertaking enforcement action; • progressing Empty Dwelling Management Orders and • delivering the Homes and Communities Agency’s Empty Homes ‘Lease and Repair contract’.

2.0Project Impact

The project can evidence considerable success in bringing longer term and more problematic empty properties back into use, including 4 properties that have been empty for over 30 years. The project has met or exceeded its targets over the last 3 years and generated a significant New Homes Bonus (NHB) income. For example, an eligible Council Tax band C property brought back into use generates about £5000 of income over 6 years and a further £2100 if it is brought back as an affordable home. (This is set out in more detail at Appendix 1)

The table below sets out the project achievement achievement and income generation to date- date

Year Number of long term NHB (over 6 years) homes back into use 2011-12 20 £ 82,853 2012-13 23 £ 84,390 2013-14 23 £119,159

Also the Empty Property Project has had a positive impact, reputationally for the Council, with the Officer having undertaken taken lead roles in the East Midlands on empty mpty homes, invited to and addressed a number of conferences, acted as an expert panellist and provided information for the Homes and Communities ommunities Agency, on empty homes good practice. 3.0 Project Going Forward

Going forward, the inclusion of the post in the base budget will ensure that the Council can continue to deliver against its Corporate priority and bring empty properties back into use. It also has the potential for the remit of the role to be expanded to include shorter term empty properties, assisting Council Tax in data checking and undertaking mail outs of all recorded empty properties.

This work has been previously undertaken by an external company, however using the empty property project post to undertake dertake the work would have the potential to further increase the NHB income for the Council.

It is therefore proposed that the project is continued on a joint basis with the City of Lincoln Council. Confirmation in December was received from the City of of Lincoln who confirmed they wish to continue with the Partnership arrangements.

Recommendations That the Empty Property Project Officer post is included in the base budget from 1st April 2014 as a 0.5 FTE post at a cost of £20,000.

IMPLICATIONS Relationship to Community Strategy Our Homes

Customer Impacts More homes, more affordable homes , less empty homes , less eyesore/problematic empty homes, positive neighbourhood impacts

Financial Impacts The project requires a budget of £20,000 for a 0.5 FTE post for 2014-15 15 Funding can be covered from the New Homes Bonus Reserve Budget

Impact on Performance and data quality Number of empty homes brought back into use

Human Resources None arising from this report

Sustainability Impact Assessment NA

Equality Impact Assessment NA

Value for Money The post generates an income for the Council by bringing empty homes back into use from New Homes Bonus Risk Management None arising from this report

Legal Considerations NA

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Empty Property Project OfficerReport 116 KB DownloadRead as text

At this meeting

Whole meeting

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies