Homes and Communities Agency Empty Homes Lease and Repair (for rent) Programme Update

Noted Scrutiny 1 paper

Performance & Resources Overview and Scrutiny Panel noted this item on Monday 9 June 2014. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

- That the report be noted.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Performance & Resources Overview and Scrutiny Panel

Purpose of report

To update Performance and Resources Scrutiny Panel on the progress of the Homes and Communities Agency’s(HCA) Empty Homes Repair and Rent Scheme

1. Introduction

1.1We are currently in the final year of delivery for the HCA’s Empty Homes Lease and Repair for Rent scheme where the Council identify suitable empty properties for the scheme and work with the owner under a lease arrangement to renovate the property and let it out.

1.2As a Council, NKDC has to apply for and secure an Empty Dwelling Management Order (EDMO), in order to offer the empty homes for rental on an assured shorthold tenancy basis. Therefore NKDC; • make an application to the First Tier Tribunal for an Interim Empty Dwelling Management Order, which is part of the Housing Act 2004. • make a Final EDMO which allows us to let the property out under an Assured Shorthold Tenancy AND . • perform the renovations and pay the owners a guaranteed rent following a deduction of our estimated costs and recovery of as much capital outlay as possible. • The Homes and Communities Agency provide £8,000 per unit based on a scheme average.

1.3NKDC is allocated £80,000 toward the cost of renovating 10 properties by April 2015. This number has been reduced from an original bid to bring 15 properties back into use. The remainder is made up from the Council’s housing renewal reserve budget. The outlay is recovered as much as possible by rent collected, a proportion of which is paid to the owner and a proportion to the Council .

2. Scheme Finances

2.1Based on current costings and an assumption of an average cost for the 10th property. It is calculated that: • Total outlay from the housing renewal reserve of £79,286.38. • £63,140.09 will be recovered over the term of the scheme, resulting in an overall impact on the reserve of £16,146.29. • This attracts £80,000 of funding from the Homes and Communities Agency.

3. Financial Benefits of scheme

3.1As stated we would be cash flowing the scheme so based on £79,000 outlay, the total impact to the authority’s housing regeneration reserve would be in the region of £16,000 at the end of the 7 years.

3.2The scheme will generate a total of £54,751.23 in New Homes Bonus for the authority (this includes the £350 element for an affordable unit).

4. Changes in Delivery of Program

4.1The project has been difficult to deliver. Due to the increased cost of renovating the homes, in part because legislation changes for EDMO’s, it has meant only properties empty over 2 years could be considered. The number of units to be delivered through the scheme has been reduced from 15 to 10. This is because with increased renovation costs( as the properties have been empty for longer ) the NKDC contribution increases, and therefore makes it more difficult to recoup this cost through the rents.

5. Current Delivery

We are currently in the process of delivering 9 properties ( see Appendix One and Two) and are working to secure a 10th property. We have identified 94 properties which are suitable for EDMO’s from the April 2014 data; these have been split into 3 groups depending on the housing need in the area. A mail out of 36 properties in group 1 was performed on the 28.4.14. In group 2 there are 19 properties and then 39 in group 3.

6. Project Overview

Delivery of the project has been challenging and resource intensive. The project has also incurred more capital cost for the authority than anticipated due to legislation changes and the need for us to apply for an EDMO to secure the property.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Homes and Communities Agency Empty Homes Lease and Repair (for rent) Programme UpdateReport 96 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Homes and Communities Agency Empty Homes Lease and Repair (for rent) Programme UpdateThis decision
  2. Homes and Communities Agency 2014 Empty Homes Lease and Repair Programme Compliance Audit ReportNoted

More from North Kesteven Performance & Resources Overview and Scrutiny Panel

All decisions
MeetingDecisionOutcome
15 Nov 2021 An introduction to a Scrutiny ReviewThat word ‘streamlined’ be removed from the recommendations. 2. That the recommendations be approved. Approved Open
25 Feb 2019 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
12 Nov 2018 DCLG Select Committee ReportIt was therefore agreed to postpone proceedings until a new Scrutiny Officer was in position and the Government Repor... Agreed Open
12 Nov 2018 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
17 Sep 2018 Forward PlanIt was agreed that items should be brought to Scrutiny at a much earlier stage. Conclusion: Members noted the Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies