North Kesteven Sports Centre Refurbishment Programme - Additional works

Noted Executive 1 paper

Executive Board noted this item on Tuesday 10 June 2014. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

To note the progress and update in relation to the proposals at the North Kesteven Sports Centre; and To recommend to Council the following additional works and funding, following the consultation and design progress: - · Roofing option 2 to overlay the existing coverings with a seamless waterproofing Pro-System for £260,000; · Pool hall heating upgrade option 1 for £220,000; · Pool hall finishes option 1 Pool tiling and option 4 Acoustic wall panels for £60,000; · Removal of the sauna and steam area; · Feasibility study and the provision of a new relocated flume £400,000; · Enhancement to learner pool area £83,000; · Removal of the Climbing Wall as originally planned; and · Additional funding for approval £1,100,000 (including provision of the new flume design survey and fees at the approved rate of 7.5%) 3. To recommend to Council t hat the additional funding requirement is funded from the New Homes Bonus Reserve.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Purpose of report

To provide an update on key areas for the refurbishment of North Kesteven Sports Centre and to seek additional funding for the project from the New Homes Bonus Reserve.

Summary

The refurbishment of the centre was approved by the Council on 19 December 2013 for £2.5m and a Project Board set up to oversee the administration, promotion and implementation of the North Kesteven Centre redevelopment on 12 March 2014.

This report provides an update to key areas of the project for consideration by the Executive Board and recommendations for additional expenditure.

Following a more detailed site survey additional works have been identified which fall outside the scope of the refurbishment life of the project (likely to fail within 10 years) These areas of concern are the roof, pool hall heating, pool tiling and acoustic panelling.

1) Roof Survey and Cost options A site survey was carried out on the 02 May 2014 by Proteus Waterproofing specialist.

The survey identified the condition of the existing roof covering in terms of remaining life expectancy is: - • Red – 1-2 years • Amber – 1-3 years • Green – 3-4 years The options to address the remaining life of the roof are: -

Option 1 – Re-roofing with a duel membrane system including insulation, an allowance for structural works and edge protection to meet building regulations requirements, with a budget estimate of £625,000.

Option 2 – Overlaying the existing coverings with a seamless waterproofing Pro-System 10 cold applied, suitable to overlay the mineral felt and asphalt roofs the budget estimate is £260,000. This would not require any additional insulation and would be covered by a 10 year warranty.

- It is therefore recommended option 2 is agreed and additional funding of £260,000 is approved to cover the works.

2) Pool Hall heating and ventilation Through the employee, contractor and public consultations specific concern has been raised as to the distribution of heat to the pool hall. A feasibility review of the system has established the plant although old is working sufficiently however the distribution system does not distribute the heat effectively.

The options to address the heat provision and distribution to the pool hall are: -

Option 1 – Full renewal of air handling system plant and air distribution system with the introduction of heat recovery to ventilation, a budget estimate of £220,000. The energy saving for this installation would be circa 40-50% for the energy to heat the pool hall. When external temperatures are around freezing potential savings will be in the region of £400 per week, the annual energy saving could be up to £8,000 per year.

Option 2 – Renewal and reconfiguration of the distribution system and upgrade to ventilation, a budget estimate of £98,000. This option offers no improved energy efficiency.

Option 3 – Installation of ceiling fans to redirect the heat to low level, a budget estimate of £25,000. This option offers no improved energy efficiency, and will add additional electrical input for fans.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North Kesteven Sports Centre Refurbishment Programme: Additional worksReport 321 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. North Kesteven Sports Centre Refurbishment Programme - Additional worksThis decision
  2. The 2020/21 North Kesteven Authority Monitoring ReportApproved
  3. The 2019/20 North Kesteven Authority Monitoring ReportApproved
  4. The 2018/19 North Kesteven Authority Monitoring Report (AMR)Approved
  5. Electoral Review of North Kesteven District Council Size Submission - DraftApproved
  6. Annual Review of North Kesteven Brownfield Land Register – Part 1Decided

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies