Audit Committee, Monday 4 August 2014 at 5.00pm

Audit Plan Monitoring

Noted Finance 1 paper

Audit Committee noted this item on Monday 4 August 2014. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

That the Internal Audit Progress Report to 30 th June 2014 be noted.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Audit Committee, 12 pages

Internal Audit

Progress Report to 30 June 2014

Date: July 2014 Contents

Introduction 1

Key Message 1

Internal Audit work completed at 30th June 2014 1

Other Significant Work 2

Audits in Progress 2

Performance Information 3

Appendices Appendix 1 – Assurance Definitions 4 Appendix 2 - Limited or No Assurance Internal Audit Reports 5-6 Appendix 3 – Internal Audit Plan & Schedule 2014/15 7-10

Contact Details: Lucy Pledge CMIIA Head of Audit & Risk Management

County Offices, Newland, Lincoln, LN1 1YG : 01522 553692  [email protected] Audit Lincolnshire – Internal Audit Progress Report

Introduction 1. The purpose of this report is to:  Advise of progress being made with the Audit Plan  Provide details of the audit work during the period  Raise any other matters that may be relevant to the Audit Committee role

Key Message 2. The 2014/15 plan is now well underway with three audits in progress and benefits subsidy claim work about to commence.

Internal Audit work completed at 30th June 2014 3. The following audit work has been completed and a final report issued:

Full Assurance Substantial Limited Assurance No Assurance Assurance

No reports No reports • ICT Application No reports Security – Civica Financials

Note: The Audit Committee should note that the assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. Definitions levels are shown in Appendix 1.

4. We are reporting one limited assurance audit in this quarter. The executive summary of this report is included in appendix 2, but the highlights are:

ICT Application Security – Civica Financials

Our review concentrated on General Ledger and Debtors and Creditors modules of Civica Financials and sought to provide independent assurance on the control arrangements in place for the system and that they are being managed and maintained appropriately.

We identified a number of areas where improvements could be made around authorising user access and access security.

Page 1 of 10 Audit Lincolnshire – Internal Audit Progress Report

Other Significant Work Other work undertaken during the period includes:

Central Lincolnshire Joint Strategic Planning Committee – Accounts sign off

This annual financial return to External Audit includes the requirement for an Internal Audit Report. We were able to support this process by completing an independent selective assessment of compliance with relevant procedures and controls expected to be in operation during the financial year. This did not identify any significant concerns or weaknesses.

Audits in Progress 5. The following 2014/15 audits are in progress:

Financial Strategy

Our audit, which is at the draft report stage, seeks to provide assurances that:

 Predicted Revenue and Capital funding and income streams for 2014/15 to 2016/17 meet the needs identified in the Council's objectives  The Medium Term Financial Strategy is realistic and sustainable

Contract Management

We are currently undertaking the field work of this review, which aims to confirm that contracts across the whole organisation are managed in accordance with corporate procedures.

Central Lincolnshire Local Plan

We are conducting this audit in conjunction with time available in the audit plans of the other partners of the Central Lincolnshire Local Planning Team. This has enabled us to propose a broad scope covering various areas including governance, project management, stakeholder consultation, quality assurance, staffing and financial sustainability. The work will be done in stages at the most suitable time of year and reports issued to all partners at various points throughout the financial year.

Page 2 of 10 Audit Lincolnshire – Internal Audit Progress Report

Performance Information 6. Our schedule of work for the 2014/15 plan has now commenced, but no audits are yet complete. As such only some Indicators can be reported on in the table below

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Plan MonitoringReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Audit Plan MonitoringThis decision
  2. Audit Committee Work PlanApproved
  3. Audit Committee Work PlanApproved
  4. External Audit PlanNoted
  5. Audit Committee Work PlanApproved
  6. Q1 and Q2 Internal Audit Plan 2026/27Approved

More from North Kesteven Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. Approved Open
20 Jul 2026 Follow Up ItemsThat the Follow-Up Items report be noted. Noted Open
20 Jul 2026 Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... Approved Open
20 Jul 2026 Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. Noted Open
20 Jul 2026 Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. Noted Open