81 DEVELOPMENT OPTIONS AT LAND ADJACENT SLEAFORD STATION
The Corporate Director presented the report to Members. The Council had purchased the former Kemira Warehouse/Grantham Road depot building on Grantham Road, Sleaford, in order to deliver a key element of its Sleaford Masterplan. This site would contribute to the Sleaford Masterplan objectives of delivering a series of perimeter car parks on the edge of the town centre.
A number of options were available in the short term to utilise the site until final plans could be established and implemented. Due to the site’s contribution to the delivery of the Sleaford Masterplan, perimeter Car Parking Strategy and Transport Strategy, it was considered that the most appropriate use for the land would be as a temporary car park. This would provide valuable car parking provision on the south side of the railway line in the vicinity of the proposed pedestrian footbridge.
Access improvements onto Grantham Road, associated works and costs would be in the region of £61,200 and could be met from the Housing Revenue Account (HRA) budget. Preparation of the site and capital car parking costs would be £38,000 and could be met from the General Fund budget, to be included in the Council Capital Programme.
In response to a question the Economic Development Manager advised Members that any temporary use of the site would be fully publicised and promoted through a communications plan to encourage maximum use of the site.
Members welcomed and were supportive of the temporary use of the site as a car park and the contribution it would provide to the delivery of the Sleaford Masterplan, perimeter Car Parking Strategy and Transport Strategy.
Vote: Unanimous
Recommended to Council:
1. The temporary re-use of the former Grantham Road depot site as a temporary car park.
2. That the road access capital cost of £61,200 be met from the HRA Major Repairs Reserve and that the car park capital costs of £38,000 be met from the General Fund, to be included in the Council Capital Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.