Performance & Resources Overview and Scrutiny Panel, Monday 9 February 2015 at 5.00pm

ICT Savings Update

Noted Scrutiny 1 paper

Performance & Resources Overview and Scrutiny Panel noted this item on Monday 9 February 2015. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

That the report be noted.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Performance & Resources Overview and Scrutiny Panel

Purpose of report

To provide information on the financial savings since the introduction of Members ICT.

Councillors have requested an update on the savings accrued since the introduction of Members ICT.

The I-pads were issued over an eight week period between Dec 13 - Jan 14. Originally plans were in place to start the reduction of paper copies of committee papers from April 2014. In actual fact, printing of committee papers was discontinued from August 2014, some five months after that original planned. Similarly, member’s blackberries were discontinued from late November 2014, as a result of ongoing contract negotiations with the mobile providers, two months after that originally planned.

These delays have therefore had an impact to the achievement of savings in 2014-15; and as the information collated goes to Dec 2014 only, it is not possible to show the total savings achieved at this stage, compared to that predicted.

This report will therefore summarise the current situation in terms of the cost of introduction, and any trend analysis which can be identified in the short term during this latter period. It is suggested that a further analysis of savings from Members ICT should be undertaken in approximately six months, once a reasonable period of operation has passed.

Cost of Provision of Members ICT

The cost of providing an I-pad, with a cover, keyboard (if required) and other accessories, as well as appropriate I-pad apps to each of the 40 members who enrolled on the scheme was £12,676.

The cost of the Modern.Gov I-Pad app was £2000.

The cost of providing formal training through an external provider to Councillors at the time of issue was £4635.

In addition, the Council also provided a significant number of hours of internal staffing resource to this project over a period of approximately 9 months. Member Blackberries

At the original business case period, 35 members held blackberries. However, by the time the Council came to the point that it would discontinue member’s blackberries, this number had reduced to 27, as (a) a number had returned them, or (b) had ceased to be members during this period; and incoming members were not provided with a blackberry, given the decision to discontinue them.

Whilst 8 members returned their blackberries during the period, unfortunately, the Council were still under contract; and the rental was charged to November 2014. Therefore the value of savings will be calculated on the full 35 members.

The cost of rental for a blackberry is £42.75 per quarter, giving a cost per year of £171 per member. Therefore on the basis of the original 35 members, the remaining savings on rental in 14-15 is £1995. Total year costs (for 15-16 for example) would be £ £5985 per year.

There is also element of call charges to be accrued. Call usage varied between members, with some making no calls or data usage, and a small number being heavy users with much bigger call and data bills. However, on average, over the 35 members originally taken into account, the average call spend for a member would be £10.62 per year Whilst this is not an exact science, an indicative savings plan for 4 months over 35 members, gives an average saving of £123.90 for the remainder of 14-15, and an average of £370 in a full year.

Savings accrued from reducing printing costs.

As previously stated, printing of committee papers continued into August. Therefore the reduction of printing charges at this time is less than first anticipated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ICT Savings UpdateReport 173 KB DownloadRead as text

At this meeting

Whole meeting

More from North Kesteven Performance & Resources Overview and Scrutiny Panel

All decisions
MeetingDecisionOutcome
15 Nov 2021 An introduction to a Scrutiny ReviewThat word ‘streamlined’ be removed from the recommendations. 2. That the recommendations be approved. Approved Open
25 Feb 2019 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
12 Nov 2018 DCLG Select Committee ReportIt was therefore agreed to postpone proceedings until a new Scrutiny Officer was in position and the Government Repor... Agreed Open
12 Nov 2018 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
17 Sep 2018 Forward PlanIt was agreed that items should be brought to Scrutiny at a much earlier stage. Conclusion: Members noted the Agreed Open