Resolved
That support for the construction of a new depot and workshop at Metheringham be reaffirmed, at the revised estimated cost of £4.2million; and 2. That the scheme be considered as part of the Council’s Capital Programme for 2015/16 onwards.
Council decided this item on Thursday 26 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That support for the construction of a new depot and workshop at Metheringham be reaffirmed, at the revised estimated cost of £4.2million; and 2. That the scheme be considered as part of the Council’s Capital Programme for 2015/16 onwards.
RECOMMENDATIONS OF THE EXECUTIVE BOARD
From Thursday, 12 February 2015
119 METHERINGHAM DEPOT AND WORKSHOPS
(This item was exempt by virtue of Paragraph 3 of Schedule 12A of the Local Government Act 1972, information relating to Information relating to the financial or business affairs of any particular person including the authority holding that information).
The Deputy Chief Executive presented the report to the Board. He reminded Members that in February 2014 Council had resolved to support the principle of purchasing land at Metheringham for the construction of a new depot and workshops. Since that time a design team had been appointed and discussions have continued with the landowners.
Concern had been raised about the adequacy of the junction from the B1189 Moor Lane giving access to the site, and whether any improvements would be required (with the consequent addition to costs). Work had been undertaken by Highways Consultants which had demonstrated that the junction does have adequate capacity for the proposed development (including the anticipated outline industrial use on the land retained by the landowners). County Council Highways had confirmed in light of this study that highway objections would be ‘unlikely’.
It was anticipated that draft Heads of Terms would be produced by the Council in February 2015, for consideration by the landowners. It was anticipated that these would be agreed in March 2015.
The design team had revised the estimated cost of the construction works at £3.95 million. The revised costs included building costs inflation due to a delayed building commencement date, fees for the Design Team and a contingency figure. This presented an increase of approximately £1million from the estimated budget approved in principle in February 2014. The Deputy Chief Executive advised the Board that this figure did not include the cost of the land purchase.
The additional costs identified were disappointing. Nonetheless there remained the need for a new depot for the reasons of capacity originally identified. Metheringham remained an ideal location for the depot, and it was unlikely that a better value solution could be attained.
If approved, the additional funding would need to be considered as part of the Council’s Capital Programme for 2015/16 onwards.
The Board considered the report. Members were very supportive of the project in principle but expressed concerns about increased costs and extended timelines. The Board noted the capacity issues at the current depot, and these issues would only increase over time with a growing population. Viability was key.
The Board asked that costs be looked at again, and that savings be made where possible.
Recommended to Council: 1. That support for the construction of a new depot and workshop at Metheringham be reaffirmed, at the revised estimated cost of £4.2million; and 2. That the scheme be considered as part of the Council’s Capital Programme for 2015/16 onwards.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Metheringham Depot and WorkshopsReport | 95 KB | DownloadRead as text |
Follow Council at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | MinutesThat the minutes of the meeting held on Thursday 14 May 2026 be approved and signed by the Chairman. | Approved | Open |
| 2 Jul 2026 | Order to Appoint Persons to North Scarle Parish CouncilThat the Council noted the report. | Noted | Open |
| 2 Jul 2026 | Food and Health & Safety Law Enforcement Plan 2026 to 2028That the two-year Food and Health and Safety Law Enforcement Plans for 2026 to 2028 be approved and adopted. | Approved | Open |
| 2 Jul 2026 | Annual Treasury Management Report 2025/26That the Annual Treasury Management Report and Prudential Indicators 2025/26 be approved. | Approved | Open |
| 2 Jul 2026 | Executive Board Report (Call-in suspended in accordance with Article 10 of the Constitution)That the Council noted the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.