That, subject to planning approval, land for 22 properties in Heckington be acquired and that the 22 properties to be constructed on the land be purchased from Lindum Construction; 2. That if required the purchase of the land be made direct from the landowner as set out in the report; 3. That the budgetary provision be made in the New Build Programme to fund the scheme, as set out in the report, and a virement to a scheme budget for these amounts from the unallocated new build budget be made; 4. That the currently programmed schemes in Willow Close and Handley Street, Heckington ... view the full minutes text for item 23a
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
(This item was exempt by virtue of Paragraph 3 of Schedule 12A of the Local Government Act 1972, information relating to Information relating to the financial or business affairs of any particular person including the authority holding that information).
The Corporate Director presented the report to the Board, for the potential purchase of land in Heckington for the construction of 22 new council homes.
Lindum Construction had a development option on land in Heckington. The landowner was working with the developer to release the land for development. Lindum had offered to sell the built out site to the Council. Working with Property Services, Lindum had produced a proposal to develop their site for 22 new council homes on behalf of NKDC, with a housing mix of: 14 x 2 bed 4 person houses (including 2 certified to passivhaus) 8 x 1 bed 2 person flats
The proposal contained the delivery of two passivhaus on site in line with the NKDC New Build, Beyond Fabric First Standards. Provision of two passivhaus offered the opportunity to learn from this innovative approach to thermal efficiency and apply the lessons learned to the wider new build programme. In addition to the two passivhaus, the remainder of the properties would be constructed to the NKDC Fabric First plus standard.
In May 2015 there were 6,190 applicants on the joint housing register covering NKDC, City of Lincoln and West Lindsey DC of which 1,611 were applicants registered for housing in North Kesteven - 14 households stated Heckington as their first choice. Sleaford demand for council housing currently exceeded supply and new build properties in Heckington would prove attractive.
The Lindum proposed cost was broadly in line with estimated NKDC build costs and represented a fair price. The scheme would be entered into the NKDC new build programme for delivery in 2015/16 and 2016/17 and a virement would be made to a scheme budget from the unallocated new build budget.
Purchase of the land would be subject to receipt of planning approval and a staged payment regime would be agreed with Lindum to cover the construction period. The Corporate Director noted that it may be more effective for NKDC to purchase the land direct from the landowner and in this case a direct payment would be made and this amount would be deducted from the payment to Lindum.
When assessed using the Council’s viability model, the proposal gave a financial payback in year 36. This represented an acceptable return on investment within the context of the Council’s new build policy.
Lindum had provided the delivery programme shown below: Planning submission - end of June 2015 Planning approval - 12 weeks Acquire site and simultaneous exchange build contract - End of October 2015 Projected start on site - December 2015 (includes time for pre start condition discharge and section agreements approval) Duration of construction - 44 weeks Projected completion - end October 2016
The Corporate Director advised the Board that there were two existing long standing schemes in the Council’s new build programme in Heckington; Handley Street and Willow Close. There were issues in delivering both these schemes and this affected the viability and value for money at present. Following additional viability work on these two schemes it was proposed that the two schemes be removed from the new build programme and replaced with the new proposed scheme. The Willow Close and Handley Street schemes would be kept under review and would be reconsidered if demand in the future warranted it.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.