Executive Board, Tuesday 21 July 2015 at 3.30pm

Financial Performance - Quarter 1

Noted Executive 6 papers

Executive Board noted this item on Tuesday 21 July 2015. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

That the financial position on the Council’s General Fund, HRA Revenue account and Capital Programme be noted; 2. That the reprofiling of the £300,000 original budget element of the Broadband scheme from 2015/16 into 2016/2017 where it was expected the LCC contribution would occur be approved; and 3. That the reprofiling £500,000 of the Traditional Structural works budget be approved, in respect of capital works at Hutson Drive, North Hykeham and St Johns Square, Bracebridge Heath; to best reflect the timings of capital expenditure in 2016/17 financial year as explained in the body of the report, and the remaining projected underspend of £70,500 would act as a contingency sum as contractors could get ahead of schedule. 1. That the financial position on the Council’s General Fund, HRA Revenue account and Capital Programme be noted; 2. That the reprofiling of the £300,000 original budget element of the Broadband scheme from 2015/16 into 2016/2017 where it was expected the LCC contribution would occur be approved; and 3. That the reprofiling £500,000 of the Traditional Structural works budget be approved, in respect of capital works at Hutson Drive, North Hykeham and St Johns Square, Bracebridge Heath; to best reflect the timings of capital expenditure in 2016/17 financial year as explained in the body of the report, and the remaining projected underspend of £70,500 would act as a contingency sum as contractors could get ahead of schedule. Actions: Russell Stone
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board, 4 pages

Purpose of the report

To report to Executive Board the financial performance and projected outturn for the 1st Quarter to 30th June 2015. Following reductions in Government funding the Council established a balanced budget through a package of savings and prudent budgeting. To maintain reserves at an appropriate level this report is intended to ensure corrective action can be taken at its earliest opportunity on variances forecast, thus managing the financial risks.

This report will support the Council’s internal control systems, thus providing support to the financial resilience criteria of the Value for Money Conclusion.

2. PROJECTED OUTTURN FOR 2015/16 - FIRST QUARTER

The General Fund Summary is attached at Appendix 1 and forecasts a deficit of £3,800. It is common at this stage for the negative budget issues to be raised by budget managers while underspends slowly materialise during the second half of the year. Significant variances experienced for the year are highlighted in the detail below, in section 4.

3. FEES AND CHARGES AND OTHER GRANT INCOME

The Council has six major income streams, derived through fees and charges, which were agreed for the 2015/16 financial year. The table below provides for the progress to date in delivering against the financial targets agreed.

Profile as at Actual Projected Income Budget 30.06.15 30.06.15 Outturn Variance (£) (£) (£) (£) (£) Land Charges 137,000 39,730 28,775 137,000 - Investment Income 280,300 72,842 80,971 280,300 - Planning Fees 865,000 216,165 242,945 925,000 (60,000) Building Control 271,300 75,964 65,400 261,300 10,000 Car Park 321,800 76,633 75,200 321,800 - Workshop Rent 325,400 64,120 49,076 325,400 - Total 2,200,800 545,454 542,367 2,250,800 (50,000) 4. SIGNIFICANT VARIANCES

The table below highlights the significant variances (over £10,000).

Variation Service Explanation of Variance (£) Our Communities

Refuse/Kerbside/Green 253,900 Recycling Credits from LCC ceasing after 1st Quarter. Use of the Income Volatility Reserve to negate the impact to the General Fund is advised, Waste (253,900) report pending. Our Economy 15,000 Costs relating to the Grow LN6 project funded through grant received (15,000) from Lincolnshire County Council Economic Development 15,000 Feasibility Study for Cranwell Aviation Heritage Trust to be funded (7,900) through grant and the regeneration budget Our Homes 15,600 Agency costs to cover long term sick and excess work Development Management (60,000) Increased demand on planning applications Building control Income Streams have significantly reduced in the first Building Control 10,000 quarter of the 2015/16. Our Council Miscellaneous Expenses 18,500 Removal of 1st Quarter vacancy allowance

Other Variances 12,600

Total Projected Outturn 3,800 NB: This figure is unadjusted for the impact from recharges Variances

5. RESERVES

The Medium Term Financial Strategy identifies the utilisation of reserves to fund the Council’s priority projects. A schedule of reserves is attached at Appendix 2, and shows the forecast balances as at 31st March 2019. 6. CAPITAL EXPENDITURE

As shown in the table below, the original capital programme for 2015/16, approved by the Board, amounted to £20.916 million. Movements in the programme since that original approval have increased the overall approved expenditure budget on schemes to £23.378 million. The Projected Outturn for the Capital Programme 2015/16 currently stands at £22.414 million. Expenditure on all capital schemes up to 30th June 2015 is attached at Appendix 3. Original Carry In Year Approved Projected (Underspend) Estimate Forwards Approvals Budget Outturn / Overspend 2015/16 2015/16 2015/16 2015/16 2015/16 2015/16 £ £ £ £ £ £

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarterly General Fund SummaryAppendix 1 1 pages Download
PDF
Reserves as at 30-06-15Appendix 2 1 pages Download
PDF
Capital Programme as at 30-06-15Appendix 3 2 pages Download
PDF
HRA Summary as at 30-06-15Appendix 4 1 pages Download
PDF
Executive Board Qtr 01 2015-16 Financial ForecastReport 4 pages DownloadRead as text
PDF
Financial Performance: Quarter 1Report 4 pages Download

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Financial Performance - Quarter 1This decision
  2. Financial Performance 2026/27 as at 30th June 2026 (Quarter 1)Agreed
  3. 2025/26 Financial performance as at 31 March 2026 – Provisional OutturnNoted
  4. 2025/26 Financial performance for the third quarter up to 31 December 2025.Agreed
  5. 2025/26 Financial performance for the second quarter up to 30 September 2025.Agreed
  6. Financial Performance 2021/22 as at 30th September 2021 (period 6)Agreed

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies