Item11b
Resolved
Approved: 1. That the tender price costs, which represent the lowest tender submitted, be approved for the works to the access road (HRA) and car park (GF). 2. That the additional monies required to deliver this project be approved from the Regeneration Reserve. 3. That the programmed HRA Access works budget be reduced to £50,000 and the programmed General Fund Car Parks budget be increased to £62,500 4. That the contingency costs identified, be split equally between the HRA and Regeneration Reserve.
Word for word from the decision North Kesteven published for this meeting.
Source: democracy.n-kesteven.gov.uk