North Kesteven District Council
Executive Board, Tuesday 20 October 2015 at 4.00pm

NKDC Risk Strategy

Approved Executive 3 papers

Executive Board approved this item on Tuesday 20 October 2015. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

That the revised strategic risks be approved. 2. That the Risk Management Strategy be approved. 3. That the immediate implementation of the Risk Management Strategy be approved. 1. That the revised strategic risks be approved. 2. That the Risk Management Strategy be approved. 3. That the immediate implementation of the Risk Management Strategy be approved.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board, 6 pages

Committee: Executive Board Meeting Date: 15th October 2015 Report presented by: Russell Stone Author: Sarah Golembiewski Email: [email protected] Tel: 282259

Report Title: Risk Management Strategy Key Decision Yes No Recommendation to Council Yes No Council Meeting Date: Is this report exempt or confidential Yes No

Purpose of Report To provide an overview of the NKDC Risk Strategy 2015 to 2018 and to seek comments and support for its implementation.

Summary Following a review of the Councils risk management strategy it has been revisited to consider how the Council can better; 1. align the Councils strategic risks more closely with the Councils priorities 2. identify, manage and report on non-strategic risks (project and operational risks)

This report will advise how recommendation has been made to CMT on amended strategic risks and introduce the new risk management strategy and the action’s necessary to ensure its effective implementation.

Strategic Risks and the Councils Priorities Currently the Councils Strategic Risks are;  Responding positively to the expected changing population including demographics, growth and health issues.  Retention of a motivated highly skilled workforce  Delivery of the new Local Plan for Central Lincolnshire  Delivery of Economic Delivery Projects  Economic growth and financial support for local businesses  Withdrawal of Central Government financial support (revenue Support Grant and New Homes Bonus) and its impact on the viability of the Council  The impact of Welfare Reform on demand for services

To align the risks with the Councils Priorities it is recommended the Council’s Strategic Risks are now;

 Technology and resources not used effectively  Delivery of key strategic projects not achieved  Inability to respond positively to the expected changing population  A workforce that is highly skilled and motivated is not maintained  Changes to Council income Each risk is seen to have a direct influence on one or more priority as shown below;

Existing Strategic Risk Revised Strategic Risk Priority

Responding positively to the Ineffective response to Our Council expected changing population demographic change Our Community including demographics, growth and health issues. Our Homes Our Economy

Resources and technology Our Council not effective Our Community Our Homes Our Economy

Delivery of the new Local Plan Delivery of Council Priorities Our Economy for Central Lincolnshire and key projects not Our Community Delivery of Economic Delivery achieved Our Homes Projects Economic growth and financial support for local businesses

Retention of a motivated highly A workforce that is not highly Our Council skilled workforce skilled and motivated in not maintained

Withdrawal of Central Increasing or unknown Our Council Government financial support financial pressures Our Community (revenue Support Grant and New Homes Bonus) and its Our Homes impact on the viability of the Our Economy Council The impact of Welfare Reform on demand for services

The revision provides the Council with strategic risks which are focused, aligned with our priorities, clear, concise and present opportunity for positive action.

With effective risk management an embedded part of the Councils planning and decision making process, the link between identifying and managing risks and the successful achievement of our objectives and vision is clearly demonstrated.

Risk Management Strategy Overview The strategy has been produced by the Governance and Business Resilience Manager and is firmly built on the principals of ISO 31000 and the Risk Management Institutes Risk Management Standard.

The strategy will enable the Council to identify, assess and manage risk in a way which supports informed decision making, creativity and innovation when meeting our corporate objectives.

The objective of the strategy is to add maximum sustainable value to all of the activities of the Council in a proportionate, timely and measureable way.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk StrategyAppendix 1 10 pages Download
PDF
Risk Strategy Implementation Action PlanAppendix 2 2 pages Download
PDF
NKDC Risk StrategyReport 6 pages DownloadRead as text

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies