iPad Efficiencies

Noted Scrutiny 2 papers

Performance & Resources Overview and Scrutiny Panel noted this item on Monday 9 November 2015. Below is the council's own wording, with the papers it was decided on.

Item47

Resolved

That the return on investment from the introduction of Ipads for Members be noted.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Performance & Resources Overview and Scrutiny Panel, 6 pages

Purpose of report

To provide information in respect of the return on investment from and actual cashable savings achieved by the introduction of Ipads for Members.

2.0Context

As reported to a previous meeting iPads were issued to Members over an eight week period between December 2013 and January 2014. It was initially planned to reduce the production of paper copies of committee documents from April 2014. Following a settling in period the printing of committee papers was eventually discontinued from August 2014.

Members’ blackberries were discontinued from late November 2014, two months after the date originally planned. This delay was caused by ongoing contract negotiations with the mobile telephone providers.

The costs in respect of the initial purchase and set up of the iPads is a known one-off cost, with the investment being provided from the ICT Replacement Fund, which has its own separate budget. It was initially anticipated that the iPads would be used for 4 or 5 years with the idea of eventually aligning future refreshes of equipment with the calendar of local elections.

This report concentrates on comparing two full calendar years, one prior to and one after the discontinuation of printing documents in bulk for committees, i.e. August 2013 to July 2014 and August 2014 to July 2015.

The report assesses the overall return against the original investment, plus the actual cashable savings achieved. The expectation in the 2014-17 Medium Financial Strategy was for cashable savings of 11k per annum to be achieved once i-pads were fully rolled out.

3.0Return on Investment & Cashable Savings: Summary

The report considers several main aspects:  Initial cost of equipping Members for the overall return on investment  Revised mobile phone provision  Costs of producing printed documents for committees  Postage and courier costs to Members  Implications on the Business Support, Reprographics, and Demographic Services teams  Summary of costs and projected savings over a 4 year project period The top level return is £63,440 over a 4 year project period, with annual cashable savings of some £13,000 being delivered. Table 1 below provides a breakdown of this, and a more detailed commentary follows thereafter.

Table 1: Summary of savings of Members ICT

On going costs Aug 2013 Aug 2014 Annual % Shift Assume Projected - Jul 2014 - Jul 2015 reduction 4 year saving £ £ £ refresh 4 year £ Mobile phones* Rental 5985 288 Call costs 372 127 5613 161 5452 97% 4 21807 Printing* 13513 10450 3063 23% 4 12253 Postage* 5166 2649 2517 49% 4 10067 Courier* 530 390 140 26% 4 560 Business Support 9045 6030 3015 33% 4 12060 Team Reprographics Team 12002 4001 8001 67% 4 32005 45869 23681 22188 48% 88751 *cashable savings Ipad Project costs One-off Annual Projected cost additional cost cost 4 year £ iPad procurement iPad, cover, other 12676 12676 accessories Modern.Gov app To access exempt app 2000 4 8000 External trainers 4635 4635 17311 25311 Net return 63440

Cashable Savings Annual 4 Year Mobile Phones 5452 21807 Printing 3063 12253 Postage 2517 10067 Courier 140 560 Repro Income (budget) 4000 16000 Mod.gov app (2000) (8000) Actual Cashable Total 13172 52688

MTFS Budgeted Cashable 11000

Actual v Budget variance 2172 4.0 Return on Investment & Cashable Savings: Detail

4.1Initial Cost of Provision of Members ICT

At the outset 40 out of 43 Members enrolled on the scheme. The initial cost of providing ICT to Members was £17,311 with a breakdown of this in Table 2 below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Summary Printing Recharges and Jobs: Aug13-Jul15Appendix 1 1 pages Download
PDF
iPad EfficienciesReport 6 pages DownloadRead as text

More from North Kesteven Performance & Resources Overview and Scrutiny Panel

All decisions
MeetingDecisionOutcome
15 Nov 2021 An introduction to a Scrutiny ReviewThat word ‘streamlined’ be removed from the recommendations. 2. That the recommendations be approved. Approved Open
25 Feb 2019 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
12 Nov 2018 DCLG Select Committee ReportIt was therefore agreed to postpone proceedings until a new Scrutiny Officer was in position and the Government Repor... Agreed Open
12 Nov 2018 Exempt InformationThat under Section 100 (a) (4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... Decided Open
17 Sep 2018 Forward PlanIt was agreed that items should be brought to Scrutiny at a much earlier stage. Conclusion: Members noted the Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies