Resolved
RESOLVED That the Draft Audit Plan for 2016/17 be approved with the inclusion of the suggested inclusion of the Asset Management ICT system as part of the audit plan.
Audit Committee approved this item on Monday 7 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Draft Audit Plan for 2016/17 be approved with the inclusion of the suggested inclusion of the Asset Management ICT system as part of the audit plan.
This report presents to the Audit Committee the proposed Internal Audit Plan for 2016/17
Internal Audit works to an annual plan of work which is agreed by the Audit Committee and Senior Management.
Our Internal Audit strategy has been developed using a risk based approach – taking into account management's assessment of risk including those set out in strategic and operational risk registers) and the assurances present thorough the Council's assurance framework (the Council's assurance map).
We use our own risk assessment against each activity assessing their significance, sensitivity and materiality – ranking the activity as high, medium or low risk. This allows us to prioritise possible areas to be included in the plan on the basis of risk.
Our aim is to align our work with other assurance functions – seeking to look at different ways of leveraging assurance to help us to maximise the best use of the Internal Audit resource and other assurance functions in the Council.
By adopting this approach it is possible to give the Council comfort that there is a comprehensive risk and assurance framework with no potential gaps. Internal Audit are then able to use our risk assessment and the assurance map to target resources to minimise duplication of effort through sharing and coordinating activities with management and other management oversight functions.
Internal Audit continues to have the right to conduct its own assurance activity freely and independently in order to meet its role and remit – even if there appears to be a good level management or alternative assurance in place. However, the Map has enabled the reasons why we have included areas in our plan to be clearly understood by Management.
Our work tends to focus on where current assurances have been critically assessed as having a low or medium level of confidence on service delivery arrangements – management of risks – effective control environment or where more independent assurance is required - based on significance and risk of the activity. It also takes into account the relative risks of the activity which may result in some low risk areas not being audited.
The plan includes: - Critical systems - those areas identified by senior management as having the most impact on the successful delivery of Council priorities or whose failure could result in significant damage to reputation, financial loss, impact on people. For example review of : o Transformation Programme o ICT Disaster Recovery o Software Licencing
- Due Diligence, those systems that support the running of the Council and ensure compliance with key policies. For example review of : o Key financial Systems o Contract management o Information Governance
- Key projects - for example assurance over : o ExCITe Project o Waste and Refuse Project o Website Project
- Emerging and strategic risk areas o Sale of High Value Housing Stock o 1% Reduction in Rent
Analysing the assurance map identified a number of specific critical and low risk activities – which we do not have the resources to review. These are shown in the attached report and the Audit Committee may wish to may wish to specifically request assurance information directly from management for those items not in the Internal Audit Plan.
Attached is the draft internal audit plan for 2016/17 – Appendix A
CIPFA's Audit Committees practical Guidance for Local Authorities and Police - 2013 Edition includes the following core functions around Internal Audit relevant to the plan:
That the Internal Audit Plan focuses on the key risks facing the Council and is adequate to support the Head of Audit opinion.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NK Audit PlanAppendix A | 2.9 MB | Download |
PDF |
Draft Internal Audit Plan 2016/17Report | 247 KB | DownloadRead as text |
Follow Audit Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | Follow Up ItemsThat the Follow-Up Items report be noted. | Noted | Open |
| 20 Jul 2026 | Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... | Approved | Open |
| 20 Jul 2026 | Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. | Noted | Open |
| 20 Jul 2026 | Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.