Recommended to Council: 1. To note the approach to CIL going forward; 2. That approval for the North Kesteven Community Infrastructure Levy Draft Charging Schedule (in Appendix 4) be confirmed for formal consultation with the supporting documents, the Draft Regulation 123 list, Draft Instalments Policy and Draft Paying CIL in the Form of Land Policy (in Appendix 6); 3. That it be confirmed that the Council would not have commented on the West Lindsey and City of Lincoln Preliminary Draft Charging Schedules if they had been consulted by them in October / November 2015; 4. That delegated authority be given to the Chief Executive to make minor amendments to the Draft Charging Schedule and supporting documents, should they be necessary; 5. That the progression of an aligned CIL examination with West Lindsey and the City of Lincoln Councils be approved, subject to the approval of the Secretary of State; 6. That the progression of the aligned CIL examination jointly with the Central Lincolnshire Local Plan be approved, subject to the approval of the Secretary of State.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Following legal advice over the procedure and presentation of the Community Infrastructure Levy the purpose of this report is to: -
Confirm to Executive Board the current programme in respect of progressing the adoption of Community Infrastructure Levy (CIL) by the Authority; To request confirmation that the Council would have made no comment on neighbouring district Preliminary Draft Charging Schedule CIL consultations; To reconfirm Member approval of the Draft Charging Schedule (DCS) for North Kesteven and consultation which is scheduled for May 2016 alongside the Central Lincolnshire Proposed Submission Local Plan; and To seek approval for North Kesteven to pursue a joint CIL/Local Plan examination in conjunction with City of Lincoln Council and West Lindsey District Council.
1.0Introduction Members will recall previous reports to Council in September 2015 and February 2016 relating to the Community Infrastructure Levy, and approval for a draft charging schedule for the purpose of public consultation. A copy of the minutes of the meeting of Council in February 2016 is attached at Appendix 1 which includes details and the resolution, which was : -
Resolved: 1. That the Preliminary Draft Charging Schedule rates for zone 2 (£20 per square metre) and zone 3 (£25 per square metre), which were consulted upon in October / November 2015 be noted and retrospectively approved for the North Kesteven administrative area;
2. That the Community Infrastructure Levy Draft Charging Schedule for the North Kesteven administrative area be approved for formal consultation with the supporting documents, the Draft Regulation 123 list, Draft Instalments Policy and Draft Paying CIL in the Form of Land Policy
3. That the Chief Executive be delegated authority to undertake minor amendments to the Draft Charging Schedule and supporting documents for the North Kesteven administrative area, should they be necessary.
Subsequent to the February 2016 Council meeting, Officers have commissioned a review of the procedural aspects of the CIL process that have been followed thus far, including a review of all supporting documentation. This review, conducted by Legal Services Lincolnshire, has identified the need to make a number of changes to the CIL documentation and associated presentation material that was previously presented to Members, in order to clarify and make it explicit that the Draft Charging Schedule approved for consultation purposes applies to the administrative boundary of NKDC only.
Members are therefore asked to confirm their approval to consult on the Draft Charging Schedule, as it is now appended to this Report, as a single Charging Schedule for NKDC as the sole Charging Authority in accordance with the Community Infrastructure Levy Regulations 2010 as amended. The Draft Charging Schedule proposal presented in this report follows an assessment of the representations made on the Preliminary Draft Charging Schedule (PDCS) that was consulted upon in October/November 2015 and an assessment of viability evidence (The Whole Plan Viability Assessment Report). It is not proposed to change the Draft Charging Schedule rate from the Preliminary Draft Charging Schedule rate.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.