Resolved
That assurance be received by the Audit Committee that internal audits were progressing.
Audit Committee decided this item on Monday 31 October 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That assurance be received by the Audit Committee that internal audits were progressing.
For all your assurance needs
NKDC - Progress Report at 30TH September 2016 Contents Para
Introduction 1
Key Messages 1-2
Internal Audit work completed at 30th September 2016 2- 4
Overdue Audit Recommendations 4
Performance Information 4
Appendices to Accompany Report
Appendix 1 – Details of Limited Assurance Reports Appendix 2 – Audit Plan & Scheduling 2016/17 Appendix 3 – Overdue Audit Recommendations Appendix 4 – Details of overdue Recommendations Appendix 5 – Assurance Definitions Appendix 6 – Performance Details
Contact Details: Lucy Pledge CMIIA Head of Audit & Risk Management
For all your assurance needs County Offices, Newland, Lincoln, LN1 1YG : 01522 553692 [email protected] Introduction
1. The purpose of this report is to:
Advise of progress made with the 2016/17 Audit Plan Provide details of the audit work undertaken since the last progress report. Provide details of the current position with agreed management actions in respect of previously issued reports Raise any other matters that may be relevant to the North Kesteven Audit Committee role
Key Messages
2. Outstanding work against the 2015/16 audit plan is now complete, two 2015/16 audits have been finalised with: Flare Application review completed. Limited assurance was provided for this review and details are recorded at paragraph 11 and Appendix 1. Payroll as a Provider report and has been completed and the detailed findings have been discussed and agreed. Limited assurance was given for this review.
3. Work continues to progress on the 2016/17 audit plan, with all but one of the scheduled reviews for completion by the end of September, now finalised.
4. The one audit outstanding is the ICT systems review and this is at draft report stage and therefore almost concluded.
5. 27% of the plan has been delivered against a quarter two target of target of 30%. See Appendix 2 providing details on the current status of the plan.
6. A review and refresh of The Internal Audit Charter has been completed and is reported separately.
7. The scheduled External Quality Assessment (EQA) of Assurance Lincolnshire was completed in September 2016; the outcome report is due mid-October and we propose to share the outcome at the next audit committee.
8. Housing Benefit Subsidy Testing was scheduled to commence in July 2016 - there has been some delays with the external auditor in obtaining the sample for testing. This work is now in progress and about 60% complete. The External Auditor deadline for completion is the end of November 2016.
9. A discrepancy was noted in the car park cash collection process and we were asked to use five days of the contingency allocation to investigate and provide a consultancy report. Our work confirmed that the discrepancy was due to a machine fault. We confirmed that robust controls are still in place and operating well for car park cash collection. This work is at draft report stage and we have made some recommendations to strengthen the overall car park cash collection and reconciliation process.
10. Good progress has been made in implementing audit recommendations - there are currently 15 overdue actions of which 6 are high priority. Further details on the outstanding actions can be found in Appendices 3 & 4.
Internal Audit work completed at 30TH September 2016
11. The following audit work has been completed and final reports have been issued since the progress report presented to the September meeting of the audit committee:
High Substantial Limited Low Consultancy Assurance Assurance Assurance Assurance
None None Flare Application None ICT Software Licensing Payroll as a provider
Note: The Audit Committee should note that the assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. Definitions levels are shown in Appendix 5.
Below are summaries of the audit reports issued. :
Flare System Review – Limited Assurance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter 2: Internal Audit Progress ReportReport | 22 pages | DownloadRead as text |
Follow Audit Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | Follow Up ItemsThat the Follow-Up Items report be noted. | Noted | Open |
| 20 Jul 2026 | Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... | Approved | Open |
| 20 Jul 2026 | Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. | Noted | Open |
| 20 Jul 2026 | Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.