Resolved
That the minutes of the meeting held on Monday 12 th March 2018 were approved as a correct record.
Audit Committee approved this item on Monday 11 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on Monday 12 th March 2018 were approved as a correct record.
NORTH KESTEVEN DISTRICT COUNCIL
MINUTES of the meeting of AUDIT COMMITTEE held at Council Chamber - Council Offices, Kesteven Street on Monday, 12 March 2018 at (6.10 - 7.37 pm)
PRESENT: Councillor Mrs S D Waring (Chairman) Councillor Mrs S J Appleby (Vice-Chairman)
Councillor M Clarke Councillor Mrs S Tarry
RESERVE Councillor T Boston MEMBERS IN Councillor C Mills ATTENDANCE: Councillor E Herring Councillor G Hazelwood
OFFICERS IN Lucy Pledge - Head of Audit & Risk Management ATTENDANCE Russell Stone - Head of Finance and Resources Dianne Downs - Internal Audit Sarah Golembiewski - Governance & Business Resilience Manager Chris Fox - Democratic Services Officer
OTHERS IN John Cornett - KPMG ATTENDANCE Simon Syddall - Independent Co-opted Member Elizabeth Venn - Independent Co-opted Member
51 APOLOGIES FOR ABSENCE AND FILLING OF CASUAL VACANCIES.
There were no apologies.
52 DECLARATIONS OF INTEREST
There were no interests declared.
53 QUESTIONS
None.
54 MINUTES
Resolved:
That the minutes of the meeting held on Monday 22nd January 2018 were approved as a correct record subject to one typographical.
55 COMMITTEE WORK PLAN 2017/18 AND 2018/19
The Head of Finance and Resources provided Members with the updated Committee Work Plans for 2017/18 and 2018/19. The Chairman asked if there was any updated information on transition arrangements between KPMG external auditors and Mazars External auditors. The Head of Finance and Resources informed the Committee that KPMG would continue to work on the 2017/18 accounts, and that Mazars would be taking over from September 2018.
In response to a question regarding the frequency of Lafford Homes Ltd on the Committee’s work plan, the Head of Finance and Resources suggested that the Committee should make sure it asked for the correct information and asked the right questions, as Lafford Homes was also heavily scrutinised by Overview and Scrutiny Panels. It was decided to keep Lafford Homes Ltd on the work plan every 6 months and review at a later date.
Resolved:
1. The Audit Committee noted the Work Plans for 2017/18 and 2018/19.
56 ANNUAL REPORT ON GRANTS AND RETURNS 2016-17
The Director of Public Sector Audit at KPMG LLP from KPMG provided the Annual Report on Grants and Returns for 2016/2017.
In answer to a question relating to the size of sample testing for Housing Benefit Subsidy, the Director of Public Sector Audit clarified that initially, 20 sample cases were examined, which was the statutory amount that had been set by the Department for Works and Pensions.
Resolved:
1. The Audit Committee noted the report.
57 EXTERNAL AUDIT PLAN 2017/2018
The Director of Public Sector Audit at KPMG provided the External Audit Plan for 2017/2018, who clarified that this was a plan of action for what areas were going to be externally audited in the near future.
The Chairman thanked the Director for his report, and suggested that the Committee had a lot of confidence in officers and auditors to achieve completion of the draft financial statements after the year end 31st March 2018, by the 31st May 2018, with final accounts to be signed off by 31st July 2018.
Resolved:
1. The Audit Committee noted the report.
58 TECHNICAL UPDATE AND EXTERNAL AUDIT PROGRESS REPORT
The Director of Public Sector Audit at KPMG provided the Technical Update and External Audit Progress Report on the summary of activities undertaken over recent months.
The Chairman asked if there would be any possible governance issues relating to the revised version of the Auditor Guidance Note 1 (AGN01), which included relevant ethical requirements for those charge with governance to be aware of; and if there would be any future effects relating to the recent guidance consultations conducted by the Department for Communities and Local Government (DCLG).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 84 KB | DownloadRead as text |
Follow Audit Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | Follow Up ItemsThat the Follow-Up Items report be noted. | Noted | Open |
| 20 Jul 2026 | Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... | Approved | Open |
| 20 Jul 2026 | Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. | Noted | Open |
| 20 Jul 2026 | Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.