Delivering the Central Lincolnshire Local Plan

Noted Planning 1 paper

Central Lincolnshire Joint Strategic Planning Committee noted this item on Monday 25 June 2018. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the Joint Committee noted the content of the report.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Central Lincolnshire Joint Strategic Planning Committee

Committee: Central Lincolnshire Joint Strategic Planning Committee

Report Title: Delivering the Central Lincolnshire Local Plan

Meeting date: 25th June 2018

Decision information Does the report contain information No which has been identified as confidential or exempt?

Report Authorisation

Report authorised by Secretariat to CLJSPC

A. Purpose of Report

 To update Members on the delivery of the Central Lincolnshire Local Plan and set out an Action Plan to accelerate housing delivery going forward.

B. Recommendations

1. That Members note the content of the report.

C. Report details

1. Introduction and background

1.1The 2012-2036 Central Lincolnshire Local Plan was adopted by the Central Lincolnshire Joint Strategic Planning Committee on 24 April 2017.

1.2The Plan sets out the policy framework to deliver sustainable growth with ambitious housing targets of 36,960 more homes in Central Lincolnshire by 2036.

1.3Not only was the Plan delivered promptly, but it has been praised as ‘what a good plan looks like’ by the Planning Advisory Service Case Study in September 2017. 1.4. Central Lincolnshire now has an effective planning framework to deliver sustainable growth and with the Local Plan’s adoption, the partner authorities’ focus has been firmly on supporting its delivery.

2. Current Housing Delivery Situation

2.1The Central Lincolnshire Five Year Land Supply Report April 2018 to March 2023 confirms that Central Lincolnshire has a 6.19 year land supply.

2.2This is positive news and evidence of the work that it is taking place to deliver the Local Plan

2.3Central Lincolnshire has also established appropriate governance and delivery teams with the;  Restructuring of the former Joint Planning Unit to create a Local Plans Team  A Central Lincolnshire Strategic Group and CLJSPC, supported by a Heads of Planning group.  Collaborative working groups and joint delivery plans, including the Section 106 Developer Obligations Supplementary Planning Document, Community Infrastructure Levy and Housing Delivery Plan working groups

3. Challenges and Opportunities for Delivery Going Forward

3.1From this strong basis, Central Lincolnshire must now further accelerate housing delivery to maintain the 5 year land supply (5YHLS) and meet the challenge of the emerging housing delivery tests set out in the National Planning Policy Framework consultation.

3.2There are opportunities and challenges as we look forward.

3.3A review of the sites within the 5YLS report highlights a number of factors;

 As an overview , there is a good level of activity on many sites with development underway, planning applications submitted or in the pipeline good level of interest in allocated housing sites  A more detailed analysis shows, unsurprisingly, that there are stronger and weaker housing markets in Central Lincolnshire, with the Lincoln Strategy Area being particularly popular but some of the outlying settlements less so.  The Sustainable Urban Extensions are the backbone of housing delivery and after the initial 5 year land supply period they will contribute in the region of 70% of the overall housing targets delivery.

3.4. In addition to analysis of the 5 year land supply report, sustainable housing growth brings other challenges, including;

2|Page  Increasing the number of developers and Registered Providers actively developing in Central Lincolnshire to increase housing and affordable housing delivery  Ensuring the delivery of infrastructure to support growth and that there is sufficient capacity amongst infrastructure providers  The need to deliver quality of design and quality of place

4. Meeting the Challenges

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivering the Central Lincolnshire Local PlanReport 145 KB DownloadRead as text

At this meeting

Whole meeting

More from North Kesteven Central Lincolnshire Joint Strategic Planning Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 Election of Chairman 2026/2027That Councillor Wright be elected Chairman of the Central Lincolnshire Joint Strategic Planning Committee for the mun... Decided Open
6 Jul 2026 Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ... Decided Open
6 Jul 2026 MinutesThat the minutes of the Central Lincolnshire Joint Strategic Planning Committee held on Monday 13 th October 2025 wer... Approved Open
6 Jul 2026 2025/26 Central Lincolnshire Joint Strategic Planning Committee Annual ReportThat the 2025/26 Annual report was approved as a fair summary of activity of the Central Lincolnshire Joint Strategic... Approved Open
6 Jul 2026 Central Lincolnshire Budget Update ReportThat the Committee noted the outturn for 2025/26 and the current budget forecast for 2026/27-2029/30 including the co... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies