Resolved
The Audit Committee noted the contents of the Internal Audit Progress update.
Audit Committee noted this item on Monday 23 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit Committee noted the contents of the Internal Audit Progress update.
NKDC – Internal Audit Q1 Progress Report 30TH June 2018 For all your assurance needs Contents Para
Introduction 1
Key Messages 1
Internal Audit work completed at 30th June 2- 5
Overdue Audit Recommendations 6
Performance Information 6
Other matters of interest 6
Appendices to Accompany Report 7
Appendix 1 – Details of Limited Assurance Reports Appendix 2 – Audit Plan & Scheduling 2018/19 Appendix 3 – Assurance Definitions Appendix 4 – Performance Details
Contact Details: Lucy Pledge CMIIA QIAL Head of Audit & Risk Management
For all your assurance needs County Offices, Newland, Lincoln, LN1 1YG 01522 553692 [email protected] Introduction
1. The purpose of this report is to:
Advise of progress made with the 2018/19 Audit Plan Provide details of the audit work undertaken since the last progress report. Provide details of the current position with agreed management actions in respect of previously issued reports Raise any other matters that may be relevant to the North Kesteven Audit Committee role
Key Messages
2. Work on the 2018/19 audit plan is progressing, with two audits in progress and two audits postponed until later in the year at management request. We have started work on the Council's Health and Safety - Doing Safety Differently project. Which looks to strengthen and improve the Council's processes and we have started the Our People workforce strategy review.
3. The postponed reviews are: the Partnership audit looking at the Local Plan Partnership and the ICT Infrastructure review.
The Local Plan Partnership is going through a major governance restructure and management have requested that the audit is postponed until this is complete.
The Corporate Director has requested that the ICT Infrastructure review is postponed until quarter two due to current workloads and commitments in the department.
4. The following audits have been completed since we last reported to committee, they are- ICT Investment Strategy – A review of the Council's ICT strategy and the detail contained within to support effective ICT planning and finance. The assurance opinion is Limited. ICT Senior Information Risk Officer (SIRO) role, advice note – This work is complete and we have shared the report with the SIRO officer. Key Controls - This is a review of the Council's key controls for Payroll, Grants Received and Treasury Management systems -considering the accuracy, effectiveness and governance around key finance controls. The assurance opinion is High. Risk Management – We reviewed the Council's use of the CAMS ICT system to record risks and completed a risk maturity exercise to gage how risk management is embedded in the Council. This is complete and the assurance opinion is Substantial.
5. Two follow up audits from the 2017/18 plan remain in progress. These are: the One Serve system review with an indicative limited assurance opinion. The final closure meeting for this is booked for the 24.07.2018.
1 the Software Licensing - we are waiting for information from the service to be able to complete the review.
6. 11% of the plan has been delivered against a quarter one target of 13%. See Appendix 2 providing details on the current status of the plan.
7. Good progress has been made in implementing audit recommendations - there are currently no overdue action to report.
Internal Audit work completed at 30th June 2018
8. The following audit work has been completed and final reports have been issued since the progress report presented to the July meeting of the audit committee:
High Substantial Limited Low Consultancy Assurance Assurance Assurance Assurance
Key Risk ICT Investment SIRO Advice Controls– Management Strategy note Treasury Management Grants Received and Payroll.
Note: The Audit Committee should note that the assurance expressed is at the time of issue of the report but before the full implementation of the agreed management action plan. Definitions levels are shown in Appendix 5.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress UpdateReport | 730 KB | DownloadRead as text |
Follow Audit Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 15 June 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | Follow Up ItemsThat the Follow-Up Items report be noted. | Noted | Open |
| 20 Jul 2026 | Audit Committee Work PlanThat the be approved. That a Local Government Reorganisation update be added to the November 2026 meeting. That housi... | Approved | Open |
| 20 Jul 2026 | Audit Committee Annual Chairman's ReportThat the Annual Chairman's Report be noted. That the report be recommended to Full Council for information. | Noted | Open |
| 20 Jul 2026 | Local Government Reorganisation (LGR) Financial and Governance Risk ReportThat the Local Government Reorganisation Financial and Governance Risk Report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.