That the financial position on the Council’s General Fund, Housing Revenue Account, Reserves and Capital Programmes for 2018/19 as at 30 th June 2018 be noted. 2. That the budget and funding for the road repair works undertaken at North Kesteven Sports Centre ( OneNK ) totalling £94,000 be approved. Where £19,600 be funded from external contributions, £24,600 be funded from other external income and £49,800 be funded from a Renewals reserve drawdown. 3. That the Disabled Facilities Grants budget be increased from £452,000 to £750,000 due to the increased grant demand this financial year. This is to be funded from ‘In year’ private contributions of £14,300 and much increased ‘In year’ Government Grant receipts of £735,700 as detailed in the appended Annex A report.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report Title: Financial Performance for 2018/19 as at 30th June 2018
Executive Board meeting 13th September 2018 date:
Council NA meeting date: Decision information Key Decision? Yes Policy Framework Proposal? No
Recommendation to Council? No Does the report contain information No which has been identified as confidential or exempt? Relevant Overview and Scrutiny Panel Performance and Resources District Wards Affected All
Report Authorisation
Report authorised by Head of Service
Russell Stone
Report authorised by Corporate Management Team Ian Fytche
A. Purpose of Report
To report to the Executive Board the financial performance and projected outturn for 2018/19 as at the three months to 30th June 2018.
The Council set General Fund and HRA balanced budgets for 2018/19 and Funded Capital Programmes for 2018/19 on 6th March 2018. At this point in the financial year, a number of variations have been identified that will impact on the financial position of the Council. A number of Budget Carry forwards were proposed to be reprofiled from 2017/18 to 2018/19. These were approved at the Corporate Management Team meeting on the 10th May 2018. B. Recommendations
1. That the financial position on the Council’s General Fund, Housing Revenue Account, Reserves and Capital Programmes for 2018/19 as at 30th June 2018 be noted. 2. To approve the budget and funding for the road repair works undertaken at North Kesteven Sports Centre (OneNK) totalling £94,000. Where £19,600 be funded from external contributions, £24,600 be funded from other external income and £49,800 be funded from a Renewals reserve drawdown. 3. That the Disabled Facilities Grants budget be increased from £452,000 to £750,000 due to the increased grant demand this financial year. This is to be funded from ‘In year’ private contributions of £14,300 and much increased ‘In year’ Government Grant receipts of £735,700 as detailed in the appended Annex A report. C. Financial risk implications
The Council has set a balanced budget for 2018/19 and has limited balances and reserves. Therefore, any potential overspend needs to be monitored and managed as the impact on the Council’s finances could be significant.
Risk analysis has been undertaken as part of the report on the current budget outcomes. Financial Services Manager 04/07/18 D. Human Resources Comments
No issues. H R Manager 10/07/18 E. Legal implications
None identified. F. Relationship to the NK Plan
None identified G. Equality Impact Assessment
Not Required Corporate Information Manager 11/07/18
2|Page H. Privacy Impact Assessment
Not Required Corporate Information Manager 11/07/18 I. Sustainability Impact Assessment
Not Required Sustainability Initiatives Officer 11/07/18 J. Consultation and communications
None identified. K. Report details
A more detailed financial report is appended at annex A. L. Conclusion and reasons for recommendation
Recommendations ensure good financial housekeeping, effective spend profiling and more accurate treasury management. M. Other options considered and reasons rejected
Not Applicable.
N. Document Information
APPENDIX NO. TITLE
Annex A Detailed Financial Performance Report as at 30-06-18 1 General Fund Summary as at 30-06-18 2 Reserves 2018-19 to 2021-22 3 Capital Programme as at 30-06-18 4 HRA Summary as at 30-06-18 BACKGROUND PAPERS Title Location of Background Papers
Financial Performance for 2018/19 as at Accountancy Services 30th June 2018 Report Author: Richard Hunt Email: [email protected] Tel: 01529 308125
3|Page
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.