Performance Framework 2019/20

Approved Executive 2 papers

Executive Board approved this item on Thursday 4 April 2019. Below is the council's own wording, with the papers it was decided on.

Item142

Resolved

That the performance framework for 2019/20 be approved. That the performance framework for 2019/20 be approved. Reason for Decision • The Local Government Act 1992 required the Council to collect, record and publish information on the Council’s performance every year. • Performance indicators were based on the NK Plan Corporate Priorities and the key outcomes for the District. Performance indicators were reviewed on a quarterly basis by the Corporate Management Team, Executive Board and the Performance and Resources Overview and Scrutiny Panel. • The Performance Framework for 2019/20 contained no fundamental changes. However, there were some target changes for the new financial year to ensure performance continued to be measured effectively. The Board noted that eleven Key Performance Indicators (KPIs) were proposed to be amended, alongside three KPIs to be deleted. The Board noted the rationale provided in relation to each of these changes, and also noted the 43 KPIs as set out within Appendix 1 of the report. • Members were pleased to see the inclusion of the ‘Our Environment’ Key Performance Indicator, KP032 Reduction in CO2 Emissions and it was noted that a report on this issues was due to be considered at a future meeting. • The Board were in agreement that the proposed framework would ensure that a robust performance framework, which the NK Plan would be measured by, would be in place for the following year. Alternative options considered and rejected (if any) None. Actions: Esther Watt, Corporate Information Manager
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Executive Board Report

Thursday, 4 April 2018

Report of: Deputy Chief Executive, Head of Corporate and Customer Services

Report Title: Performance Framework 2019/20

Classification: Open

Decision information Esther Watt, Corporate Information Lead Officer Manager [email protected] N Key decision?

Recommendation to Council? No

Relevant Overview and Scrutiny Panel Performance and Resources OSP District Wards Affected (All Wards); Division Corporate and Customer Services Relevant Corporate Priority Our Council;

A. Purpose of Report / Situation

 To set out the proposed performance framework with which progress of the NK Plan will be measured in 2019/20.

B. Recommendations

1. That the performance framework for 2019/20 be approved.

C. Finance and risk implications

There are no financial implications in relation to this report.

Completed by: Senior Accountant 04/02/2019 D. Human Resources Comments

No H R implications.

Completed by: H R Manager 03/02/19 E. Legal implications

The Local Government Act 1992 requires the Council to collect, record and publish information on our performance every year.

F. Impact Assessments

No Equality Impact Assessment required, as no equality impacts will arise now or in the future from the recommendations.

Completed by: Corporate Information Manager 03/02/19

No Data Protection Impact Assessment required, as no data protection impacts will arise now or in the future from the recommendations.

Completed by: Corporate Information Manager 03/02/19

No Sustainability Impact Assessment required, as no sustainability impacts will arise now or in the future from the recommendations.

Completed by: Sustainability Policy and Programme Manager 06/02/19

G. Consultation and communications

1. The Performance Framework was reviewed by the Performance and Resources Overview and Scrutiny Panel (P&R OSP) at their meeting on the 25 February 2019. The Panel welcomed the early involvement and noted the report and amendments presented for 2019/20. In addition, there were some individual Panel Member observations including:

1.1It was noted that KP048 (% of actual Right to Buy sales in the previous year replaced by new homes provided in the current year) was proposed to be deleted as part of the performance framework for 2019/20. However, the Panel were assured that the results would continue to be reported as part of the Annual New Build Report.

2|Page 1.2 A query was raised regarding KP009 (Per capita reduction in CO2 emissions) and how this was calculated and measured to ensure effectiveness.

1.3Members noted the two new KPIs under the ‘Our Environment’ Corporate Priority relating to sustainable products and biodiversity levels. Whilst agreeing these were important areas to measure, they requested further information regarding the calculation methods.

1.4A question was raised regarding one of the new KPIs under the ‘Our Communities’ Corporate Priority. This related to the % of residents who engage, participate or attend arts activities at least three times per year. The measure is built around the Department for Culture, Media and Sport’s annual ‘Taking Part’ survey, which enables the Council to benchmark nationally and regionally. The 2018 survey returned 1,600 respondents with a 33% score. As this was the first year of assessing using this method, the Council has only set a 2% growth target.

The 2019/20 performance framework will be available on the Corporate Website. Agendas, minutes, and audio recordings of all Executive Board and Performance and Resources Overview and Scrutiny Panel meetings are also available on the corporate website.

H. Report details / background

1. Performance indicators are based on the NK Plan Corporate Priorities and the key outcomes for the District.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Performance Framework 2019/20Appendix 1 258 KB Download
PDF
Performance Framework 2019/20Report 160 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Performance Framework 2019/20This decision
  2. Performance Framework 2026-28Approved
  3. Performance Framework 2020/21Noted
  4. Draft Performance Framework 2018-2019Approved
  5. Draft Performance Framework 2018-2019Approved
  6. Performance FrameworkApproved

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open