North Kesteven District Council
Executive Board, Thursday 27 June 2019 at 3.00pm

NK Plan Quarter 4 Performance 2018/19

Approved Executive 2 papers

Executive Board approved this item on Thursday 27 June 2019. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That Quarter 4 Performance progress be approved. That Quarter 4 Performance progress be approved. Reason for Decision • The Local Government Act 1992 required the Council to collect, record and publish information on the Council’s performance each year. • The NK Plan 2018-21 was prepared following extensive consultation with residents, businesses, partners and colleagues. The NK Plan responded to the main challenges facing the district, ensuring that the Council uses its resources and influence to deliver priorities and services needed by communities across North Kesteven. • Overall the Council had 39 Key Performance Indicators (KPIs) being reported on during Quarter 4 of 2018/19 with - 77% had achieved their target (30) - 3% had not achieved their target (1) - 15% had not achieved their target (6) - 5% had data still pending (2) • An overview of indicators currently showing as ‘off track’ was provided and explained. Members discussed these indicators in detail. • It was noted that in relation to KP016 Visitor Numbers attending NK Arts Partnership Events, activities and education, including NCCD, a re-programme for arts delivery had taken place during Quarter 4, with a new style of curation. Members considered that this indicator was an example of a target with challenging goals and congratulated the team on achieving a significant increase in visitor numbers. • The Board further discussed KP048 – Percentage of actual Right to Buy sales in the previous year, replaced by new homes provided in the current year and KP049 – Total amount of current arrears (excluding direct debit payers), noting the action plans in place for improvement. • In relation to KP043 – Percentage of residents who agree that streets are clean in the district, the Board noted that this responsibility was in shared ownership with other authorities and encouraged future discussions. Alternative options considered and rejected (if any) None. Actions: Esther Watt
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Executive Board Report

Thursday, 27 June 2019

Report of: Deputy Chief Executive, Head of Corporate and Customer Services

Report Title: NK Plan Quarter 4 Performance 2018/19

Classification: Open

Decision information Esther Watt, Corporate Information Lead Officer Manager [email protected] N Key decision?

Recommendation to Council? No

Relevant Overview and Scrutiny Panel Performance and Resources OSP District Wards Affected (All Wards); Division Corporate and Customer Services Relevant Corporate Priority Our Council;

A. Purpose of Report / Situation

 The purpose of this report is to review performance as at the end of the fourth quarter (to 31 March 2019) for the delivery of the Council’s priorities as described in the Corporate Plan – The NK Plan 2018-21.

B. Recommendations

1. That Quarter 4 performance progress, as described within Appendix 1, be approved. C. Finance and risk implications

There are no financial implications in relation to this report.

Completed by: Senior Accountant 13/05/19 D. Human Resources Comments

No H R implications.

Completed by: H R Manager 08/05/19 E. Legal implications

The Local Government Act 1992 requires the Council to collect, record and publish information on our performance every year.

F. Impact Assessments

No Equality Impact Assessment required. Report’s recommendations will not result in any equality impacts now or in the future.

Completed by: Corporate Information Manager 07/05/19

No Data Protection Impact Assessment required. Report’s recommendations will not result in any data protection impacts now or in the future.

Completed by: Corporate Information Manager 07/05/19

No Sustainability Impact Assessment required. Report’s recommendations will not result in any sustainability impacts now or in the future.

Completed by: Sustainability Policy and Programme Manager 13/05/19

G. Consultation and communications

Agendas and minutes of all Executive Board meetings are available on the corporate website.

2|Page H. Report details / background

2018/19 NK Plan Quarter 4 Performance

Key and Service Performance Indicators

1. The NK Plan 2018-21 was prepared following extensive consultation with residents, businesses, partners and colleagues. The NK Plan responds to the main challenges facing the district, ensuring that the Council uses its resources and influence to deliver priorities and services needed by communities across North Kesteven aligning to the Council’s vision of ‘A district of flourishing communities’. . 2. The NK Plan has four community focused priorities, and one organisational focused priority during 2018/19.

3. Performance progress against each priority as at 31 March 2019 is summarised within Appendix 1. For each KP the Council’s performance management system generates as Red – Amber – Green (RAG) traffic light rating.

o Green – have achieved their target (are on or above the year to date target) o Amber – have not achieved their target, but are within variance (below the year to date target but within an agreed tolerance level) o Red – have not achieved their target (below the year to date target and outside an agreed tolerance).

4. Overall the Council has 39 Key Performance Indicators (KPs) being reported on during Q4 of 2018/19:

o 77% have achieved their target (30) o 3% have not achieved their target (1) o 15% have not achieved their target (6) o 5% have data still pending (2)

5. The red indicators at the end of Q4 2018/19 are:

o Our Homes KP048 Percentage of actual Right to Buy sales in the previous year, replaced by new homes provided in the current year

The number of Right to Buy Sales in 2017/18 increased to 34, and the number of new homes provided in 2018/19 was 18. The total number of Right to Buy Sales from 2011/12 to 2017/18 was 134, and the total number of new homes provided from 2012/13 to 2018/19 was 173, meaning that cumulatively, 39 more new homes have been delivered than have been lost through Right Buy in the seven years since the “reinvigorated” Right to Buy policy was implemented.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for NK Plan Quarter 4 Performance 2018/19Appendix 1 769 KB Download
PDF
NK Plan Quarter 4 Performance 2018/19Report 296 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. NK Plan Quarter 4 Performance 2018/19This decision
  2. NK Plan Quarter 2 Performance Report 2026/27Approved
  3. NK Plan Quarter 1 Performance Report 2026/27Approved
  4. NK Plan Quarter 4 Performance Report 2025/26Approved
  5. NK Plan Quarter 3 Performance Report 2025/26Approved
  6. NK Plan Quarter 2 Performance Report 2021/22Decided

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies