That a scheme of investment towards the delivery of the project be approved; seeking to regenerate an area in Sleaford Town Centre by developing a new cinema and food court, associated areas of public open space, including a pedestrian footbridge over the river Slea connecting Money’s Yard to Market Place. (The total cost of the scheme was estimated at £4.0m, of which £1.5m was already committed and £0.6m represented public realm works). 2. That a further budget of £2.5m be approved to fund ... view the full minutes text for item 29a
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
In April 2018, the Council approved a scheme of investment for the Heart of Sleaford regeneration project, incorporating a new cinema development and public realm. The report presented a new enhanced project proposal that had evolved following detailed consideration of the commercial opportunities available to support the regeneration objectives of the wider Sleaford Masterplan. The key elements of the new scheme were noted in detail.
The Board noted the finance and risk implications. The scheme funding requirement could be funded from available reserves balances, predominantly the ‘New Homes Bonus’ and ‘Our Economy’ reserves. The increased drawdown from reserves was already factored into reserve usage forecasts. The full financial analysis for the proposed scheme was noted.
Legal advice had been sought both internally and externally in order to provide a satisfactory legal framework for project delivery. The details of the framework were noted.
A number of historic surveys had been analysed and had shown that a cinema remained the single most popular attraction desired by the town’s residents.
The design would feature a larger cinema and restaurant area combined in a single building, and would make the best use of the available space and create a more coherent and accessible ‘public realm’ with clear lines of site from Money’s Yard and Market Place.
The Board were in agreement that the scheme would provide a commercially viable option, with a broad public appeal. The proposal also fulfilled a key aspect of the Sleaford Masterplan and regeneration objectives. Alternative options considered and rejected (if any)
1. An alternative town centre site already had been considered for development. Calculations showed that the return on investment was slightly inferior. The Sleaford Masterplan ‘Moneys Yard to Market Place link’ would also not be delivered.
2. Smaller cinema (2-screens) and separate restaurant: Not viable as separate commercial entities given the return on investment required by the Council. A smaller cinema made consumer offer less competitive and limited availability and choice.
3. Just 3-screen cinema and not restaurant; loss of heritage undermined wider regeneration objectives. Cinema attractiveness to operator and offer to consumers diminished by loss of food concessions. Food was considered an important part of the overall Cinema package and represented the highest margin component of any cinema business.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.