Resolved by Executive Board: 1. That the proposal by Glennmont Partners to set up a new Community Benefit Fund be noted. 2. That the criteria for the operation of the fund and its geographical coverage be noted. 3. That the fund operate for a period of 5 years starting with effect from the first meeting date of the new panel that will oversee the fund. 4. That authority be delegated to the Chief Executive to approve the final Terms of Reference for the panel, following consultation with the Leader. Recommended to Council 1. That consideration be given to the selection of the three members on the new panel, including at least one member from the Executive Board.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report of: Chief Executive, Economy and Place Director
Report Title: Proposed Glennmont Community Development Fund
Classification: Open
Decision information Alan Gray, Economic Development Lead Officer Manager [email protected] No Key decision? Yes. Council meeting date: 3rd Recommendation to Council? October 2019 Communities and Economy OSP Relevant Overview and Scrutiny Panel Sleaford Navigation; Sleaford Westholme; Sleaford Quarrington and Mareham; Sleaford Holdingham; Sleaford Castle; Leasingham & Rauceby; Ashby- District Wards Affected de-la-Launde & Cranwell; Kirkby- La-Thorpe & South Kyme; Heckington Rural; Billinghay,Martin & North Kyme; Ruskington ;Osbournby(All Wards); Development, Economic and Division Cultural Services Our Communities; Our Economy; Relevant Corporate Priority Our Environment
A. Purpose of Report / Situation
Glennmont Partners, owners of the Sleaford Renewable Energy Plant, wish to set up a new Community Benefit Fund to support local groups and organisations. Glennmont have stated they wish to commit £25,000 per annum to this fund for a period of 5 years, a total of £125,000. The fund is aimed at supporting projects which cover the environment, sport and wellbeing and education. Glennmont wish the new fund to be administered by NKDC in a similar vein to the way the initial Community Wellbeing Fund, which was wound up on April 2nd 2019.
B. Recommendations
To resolve: 1. That the proposal by Glennmont Partners to set up a new Community benefit Fund be noted. 2. That the criteria for the operation of the fund and its geographical coverage be noted. 3. That the fund operate for a period of 5 years starting with effect from the first meeting date of the new panel that will oversee the fund. 4. That authority be delegated to the Chief Executive to approve the final Terms of Reference for the panel, following consultation with the Leader.
Recommended to Council 1. That consideration be given to the selection of the three members on the new panel, including at least one member from the Executive Board, and who are representative of any of the Wards falling within the geographical area which the proposed Fund will be administered within.
C. Finance and risk implications
NKDC employs suitably qualified finance staff and is capable of acting as the 'Accountable Body' for this proposal
Completed by; Strategic Finance Manager
D. Human Resources Comments
No H R implications.
Completed by: H R Manager 04/06/19
E. Legal implications
The operation and decision making processes adopted by the panel will require to conform to all the legal requirements of the Council as outlined in its constitution.
F. Impact Assessments
2|Page As this report is seeking endorsement to set up a community panel and agree its membership to oversee the allocation of Glennmont Community Benefits, no impact assessments are required at this point in time.
G. Consultation and communications
This panel will be making decisions on how the community funds offered up by Glennmont are to be spent. In this respect publicity around these decisions will be required to promote the community schemes that benefit from the fund.
In addition, publicity and communication will be required to make those eligible parishes aware, and to inform them of the criteria that will apply, in making applications to this fund for funding. The exact details of how the scheme will operate will be for the panel to determine through their initial meetings.
H. Report details / background
1. Background Information
1.1Glennmont Partners are the owners of the Sleaford Renewable Energy Plant. At the time the plant was built, there were a series of community benefits bestowed on the local communities, including a community benefit fund as part of a wider Wellbeing Agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.