Old Sidings Masterplan Update

Decided Executive 1 paper

AI summaryNorth Kesteven Executive Board endorses launch of the Old Sidings masterplan for Sleaford, to be drawn up with Feilden Clegg Bradley Studios, with £5 million earmarked for council-owned sites.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNon-statutory framework, delivery plan, investment prospectus
Money£5 millionCapital Investment Programme allocation for council sites
What happens nextFour-stage masterplanning processIncluding two public consultation stages
Who it affectsSleaford Old Sidings areaCouncil-owned sites and surrounding opportunity area

What was decided

The Executive Board endorsed the launch of the Old Sidings masterplan, to be delivered in partnership with Feilden Clegg Bradley Studios LLP. Report 3.1

The masterplan will create a non-statutory framework, delivery plan and future investment prospectus for the area. Report 1.2, 4.1

Why

The council acquired key sites between 2017 and 2025, and considering them in isolation would miss wider development opportunities for the town. Report 2.2, 2.3

The work aligns with the 'Our Economy' priority of the NK Plan 2024-2028 by aiming to attract investment and support regeneration. Report 2.1

The scale and complexity of the area means outcomes are unlikely to be achieved by the council acting alone, requiring partner involvement. Report 2.5

What happens next

FCBStudios will lead a four-stage masterplanning process, with outputs reviewed by an officer working group and approved by a project board. Report 3.1, 5.1, 6.1

Two stages of public consultation will take place, alongside ongoing stakeholder and elected member engagement. Report 5.4, 6.2

On completion, consideration of formal adoption will follow the council's constitution, setting out a 20-year vision with indicative phasing and costed interventions. Report 4.1, 6.3, P33

The money

  • £5 million Allocation through the Capital Investment Programme for the council-owned sites, subject to a future business case Report 2.4

Options considered

  • Rejected: Do nothing and do not commission a masterplan. Would fail to build confidence in local investment and delay a coordinated plan for a strategically important area Report P35
  • Rejected: Masterplan covering only council-owned sites. Would miss a holistic understanding of opportunities and challenges and risk failing to unlock longer-term strategic opportunities Report P36

Implications

  • Financial: £5 million is earmarked from the Capital Investment Programme, but any spend is subject to a future business case. Report 2.4
  • Legal: The masterplan is non-statutory and formal adoption will be considered under the council's constitution on completion. Report 1.2, 6.3
  • Other: Project complements renewed regional and national interest in the Bass Maltings, recently featured in the Historic England Investment Prospectus. Report P32

Who and where

  • Residents and communities in Sleaford and the Old Sidings opportunity area Report 1.1, 5.4
  • Partners, investors, landowners and developers with interests in Sleaford Report 1.2, 2.5
  • Council-owned sites: former Tec Foods site, Carre Arms Hotel, and Bryans Land Report 2.2, 2.4

Timeline

  • 2017 to 2025: Council made strategic land acquisitions at the former Tec Foods site, Carre Arms Hotel and Bryans Land Report 2.2
  • 20-year horizon: Masterplan will set out a long-term vision with indicative phasing and costed interventions Report 4.1, P33
  • During all four stages: Two stages of public consultation and ongoing stakeholder engagement will take place Report 5.4

Plain English for the jargon

  • Non-statutory framework: A planning document that guides decisions but does not have the legal force of a local plan
  • Investment prospectus: A document setting out opportunities and likely returns to attract potential funders and investors
  • Old Sidings: An opportunity area in Sleaford including former rail sidings and nearby council-owned sites
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

To endorse the launch of the Old Sidings masterplan, which would be delivered in partnership with Feilden Clegg Bradley Studios LLP, creating a non-statutory framework, delivery plan, and future investment prospectus.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Official

Executive Board Report Thursday, 24 September 2026

Report of: Chief Executive, Head of Investment Report Title: Old Sidings Masterplan Update Classification: Part Exempt, Appendix 1 Exempt Only under paragraph 3 of Schedule 12A of the Local Government Act 1972 as the appendix contains information relating to the financial or business affairs of any particular person (including the authority holding that information).

Decision information Mieke Alcock, Ryan Goymer, Senior Investment Project Officer, Lead Officer Investment & Corporate Programme Manager [email protected], [email protected] Key decision? N

Recommendation to Council? No

Relevant Scrutiny Committee Flourishing Communities Sleaford Castle; Sleaford District Wards Affected Navigation; Sleaford Quarrington and Mareham; Division Investment Relevant Corporate Priority Our Economy;

A. Purpose of Report

 This report provides Executive Board with an update on the Old Sidings Masterplan following completion of the procurement process and the appointment of Feilden Clegg Bradley Studios LLP (FCBStudios) as the Council’s masterplanning consultant.

 The report sets out the strategic purpose of the masterplan, the outcomes the Council is seeking to achieve, and seeks endorsement for the next phase of work to develop a deliverable, investment-ready and community-informed masterplan for the Old Sidings opportunity area.

B. Recommendations

To resolve:

To endorse the launch of the Old Sidings masterplan, which will be delivered in partnership with Feilden Clegg Bradley Studios LLP, creating a non-statutory framework, delivery plan, and future investment prospectus. Official

C. Finance implications

There are no financial implications relating directly to this report. A previous report (Acc25-26/Ref108) has been submitted which sought approval of expenditure from the Investment budget to fund consultancy work relating to this project. Any future expenditure will require additional reports.

Completed by: Accountant (Acc26-27/Ref128/CW) Dated: 21/08/2026

D. Human resources comments

No H R implications.

HR 26-27 Ref 137 Head of People and OD 19/08/2026

E. Risk assessment

Risk registers will be maintained throughout the development of the masterplan, both by the appointed consultant and internally by the Project Board.

F. Legal implications

There are no legal implications associated with this report.

G. LGR implications

It is not expected that Local Government Reorganisation will directly impact the masterplanning process outlined within this report, as we expect the contract to conclude in June 2027.

There are likely to be implications for the longer-term implementation of projects or interventions identified within the masterplan, and this will therefore form an important consideration throughout the identification of projects and creation of the delivery strategy.

This will be monitored as Local Government Reorganisation progresses.

H. Impact assessments

Equality

This report is for information only, and at this stage does not require an Equality Impact Assessment as it is currently too early to understand the impact. However, this will be reviewed in due course as additional information becomes available.

Data protection

2|Page Official

This report is for information only, and at this stage does not require a Data Protection Impact Assessment. However, this will be reviewed in due course as additional information becomes available.

Sustainability

No Sustainability Impact Assessment is required as this report is for information only and has no direct environmental or climate impacts. Any subsequent or associated reports which follow may need to be assessed separately to determine if an SIA is required.

I. Consultation and communications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Old Sidings Masterplan UpdateReport 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
RH
Richard HuntCouncil Staff, expected
RW
Councillor Richard WrightChairman, expected
IC
Councillor Ian CarringtonVice-Chairman, expected
MM
Councillor Mrs Mary GreenMember, expected
MS
Councillor Mark SmithMember, expected
MS
Councillor Mrs Sally TarryMember, expected
KM
Kath MarriottOfficer, expected
SH
Steve HouchinOfficer, expected
CE
Catherine EvansOfficer, expected
TA
Tracy AldrichOfficer, expected
KR
Kim RobertsonOfficer, expected
KS
Kit SilcockSecretary, expected

All 20 on the meeting page

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies