New two Form of Entry Primary School on the Stanton Cross Sustainable Urban Extension (SUE) development

Approved Executive

Executive approved this item on Thursday 5 August 2021. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

(KEY DECISION) a) That the Section 106 expenditure of £9.66 million to fund the new 2FE primary school, located on Stanton Cross, SUE, be approved; b) That the inclusion in the Council’s capital programme of a new two form entry primary school situated on the new SUE at Stanton Cross, Wellingborough be noted; c) That the necessary contract awards for Stanton Cross, following the procurement process and proceed with the construction on the new school, with a proposed opening date of September 2022, be authorised; d) That the financial and governance arrangements associated with the capital scheme be approved; e) That authority be delegated to the Portfolio Holder for Children, Families and Education in consultation with the Director of Children’s Services to authorise all necessary contract awards to deliver the new school; f) That it be noted that the process to appoint an Academy Sponsor to run the new school, in accordance with the ‘Free School Presumption’ regulations, stipulated by the Department for Education, will commence. (Reasons for · The Local Authority has a legal obligation to deliver the primary school, in accordance with the signed section 106 agreement; · The recommended course of action will allow the timely progression of capital works to build the new primary school at Stanton Cross SUE; · The recommended course of action will benefit students and families who will reside within the development, by providing local school places for local school children; · North Northamptonshire Council (or customers) will receive the maximum benefit from the option proposed.) · The Local Authority has a legal obligation to deliver the primary school, in accordance with the signed section 106 agreement; · The recommended course of action will allow the timely progression of capital works to build the new primary school at Stanton Cross SUE; · The recommended course of action will benefit students and families who will reside within the development, by providing local school places for local school children; · North Northamptonshire Council (or customers) will receive the maximum benefit from the option proposed.)
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies