Capital Programme Update 2022/23

Approved Executive 1 paper

Executive approved this item on Thursday 15 September 2022. Below is the council's own wording, with the papers it was decided on.

Item297

Resolved

RESOLVED KEY DECISION That the Executive: i) Approved the following changes to the capital programme: a. Disabled Facilities Grant – to increase the capital budget available in 2022/23 for associated works and services to £2,561,759 in accordance with the grant award. An indicative sum of £1.9m was already included in the budget assumptions for 2022/23 and, therefore, this represents an increase of £0.662m. b. Kingswood Urban Development - £86,900 increase to the capital budget funded through external contributions. a. Housing Stores Project – virement of £162,820 to this scheme – funded from an existing capital budget underspend within the Housing Revenue Account (HRA) capital budget. b. Cannock Road Housing Development – virement of £454,000 to this scheme – funded from existing capital budget within the HRA capital budget. ii) Recommended to Council to approve the additional virement in support of the Cannock Road housing development as the total virement requested for this scheme, including previous transfers, exceeds £0.5m. Reasons for Recommendation: these are set out in greater detail within section 5 of the report, but can be summarised as: · To expand the capital budget available to support disabled facilities within homes. · To replace and improve the skate park as part of Kingswood Urban Development. · To improve the stores arrangements at Corby and Kettering depots through a new single system designed to hold appropriate stock levels to meet housing repair needs. · To improve and expand the housing provision in North Northamptonshire. Alternative Options Considered: · For external funding (DSG and Kingswood Urban Development) - use of the funding is in line with the agreements, there is no alternative option proposed. · By not approving the stores recommendation the Council would not be able to improve productivity in respect of housing repairs. · There is not an alternative option for the Cannock Road housing development. This is an approved scheme that is already in progress.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update 2022/23Report 146 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Capital Programme Update 2022/23This decision
  2. General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030Approved
  3. Capital Programme Update 2025/26Noted
  4. Capital Programme Update 2025/26Approved
  5. Capital Programme Report 2025-2029Approved
  6. Capital Programme Update 2024/25Approved

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies