Executive, Thursday 10 November 2022 at 9.00am

Street Lighting LED Upgrade

Approved Executive 3 papers

Executive approved this item on Thursday 10 November 2022. Below is the council's own wording, with the papers it was decided on.

Item329

Resolved

RESOLVED KEY DECISION That the Executive: a) Confirmed approval to proceed with the LED replacement and Central Management System (CMS ) upgrade of streetlights within the PFI agreement with Connect Roads/ Balfour Beatty. b) Delegated authority to the Executive Member for Highways, Travel and Assets, in consultation with the Executive Member for Finance, the Executive Director for Finance and the Executive Director for Place and Economy to: i. secure and allocate appropriate funding, through Prudential Borrowing; ii. agree the necessary changes to the PFI funding agreement with Connect Roads/Balfour Beatty to complete the required works. Reason for Recommendations: The recommendations will deliver against the Council’s priorities to provide efficient services that deliver value for money, whilst maintaining a safe public highway and reduce carbon emissions in line with the Council’s commitment to becoming carbon net zero by 2030. Alternative Options Considered: · An alternative is to continue with the current street lighting lanterns, which would avoid the need to provide capital funding for investment. This option would not deliver the financial, social or environmental objectives of the proposed recommendations · It would be possible to change the lanterns to LEDs, but not install the CMS. This would not deliver the operational and potential financial and environmental benefits of having remote control over the network of streetlights, so this is not recommended. · The Council owns and manages streetlights, inherited from the former district and boroughs, which are not part of the street lighting PFI. In order to convert those assets to LED, they would first need to be transferred into the PFI. It is not proposed to transfer those assets to the PFI through this project as it will require additional inspection and upgrade of those assets in order to meet the strict specification requirements of the PFI. This is a separate consideration, and investment, that the Council may want to explore at another time.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
ESA Streetlighting LEDAppendix A 166 KB Copy on its way
PDF
Street Lighting ModelAppendix B 53 KB Copy on its way
PDF
Street Lighting LED UpgradeReport 161 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Street Lighting LED UpgradeThis decision
  2. Street Lighting LED UpgradeNoted

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies