Schools Education Capital Programme Business Case - Wollaston Secondary School SEND Unit Extension

Approved Executive 1 paper

Executive approved this item on Thursday 16 March 2023. Below is the council's own wording, with the papers it was decided on.

Item409

Resolved

RESOLVED KEY DECISION That the Executive : i) Approved the proposed scheme subject to budget allocation from the Department for Education (DfE) Higher Needs Funding Allocation and planning approval. ii) Noted the scheme is to be delivered through a Funding Agreement with The Nene Partnership to enable the Wollaston Secondary School to provide additional SEND Places and support the Local Authority to discharge its statutory duty to provide sufficiency of SEND places in Wellingborough. iii) Delegated authority to the Executive Member for Children, Families and Education in consultation with the Director of Children’s Services, to authorise all necessary legal, property and financial agreements to ensure effective delivery of the project. Reasons for Recommendations: · The school facilities are limited and stretched; several students have significant high-level needs which the school is struggling to meet. The recommendations support an increase in facilities. · The proposal will increase the number of quiet spaces for students with SEND. · During exams there is insufficient space to support students with their access arrangements, the proposal support an increase. · The recommendations support the Council to address the lack of Sufficiency of SEND Places across North Northamptonshire particularly Secondary places. · Under school place planning duties (s13-14 Education Act 1996) the Council as an education authority has a duty to promote high standards of education and fair access to education including SEND. · The Council has a general duty to secure sufficient schools in their area. This includes a duty to respond to parents’ representations about school provision. These are referred to as the school place planning duties. · Failure to provide sufficiency of places would also result in increased home to school transport costs as students would need to be transported to other areas of the County and outside of North Northamptonshire. Alternative Options Considered: Option 1: To do nothing and continue with inadequate SEND facilities at the school. This option is not recommended as not increasing SEND facilities does not support the Council to discharge its statutory duty to provide sufficiency of SEND places within North Northamptonshire. Option 2: To construct a single storey extension that will create 2 teaching spaces of 30m 2 which will accommodate 12 students with complex needs. The preferred option is Option 2 as it increases the availability of SEND places. This option provides appropriate expansion and enhancement of the existing school and meets the growing demand of SEND school places in North Northamptonshire. Option 2 also supports the council’s ability to meet its statutory responsibilities to provide a sufficiency of school places in North Northamptonshire. Provide appropriate expansion of existing school to enhance inclusivity, diversity and equality for the SEND students. This project is subject to the budget and planning approval for the construction of the proposed SEND Unit.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Schools Education Capital Programme Business Case: Wollaston Secondary School SEND Unit ExtensionReport 160 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Schools Education Capital Programme Business Case - Wollaston Secondary School SEND Unit ExtensionThis decision
  2. Schools Education Capital Programme Business Case – Kingsley Special School Mobile Unit ReplacementApproved
  3. Schools Education Capital Programme Business Case – Little Stanion School Roof ReplacementApproved

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies