Executive, Thursday 20 April 2023 at 10.00am

Capital Programme Update 2023/24

Approved Executive 1 paper

Executive approved this item on Thursday 20 April 2023. Below is the council's own wording, with the papers it was decided on.

Item424

Resolved

RESOLVED KEY DECISION That Executive approved the following changes into the capital programme: a) Kingsley Special Academy new building to replace mobile classroom, to be moved from the Development Pool into the Capital Programme - £1.432m; £222k in 2023/24, £1.134m in 2024/25 and £72k in 2025/26, which is to be funded from Special Educational Needs and Disabilities (SEND) Capital grant. b) Corby Town Investment Plan, Project 2 Multi-use building – £1.5m; £0.7875 in 2023/24 and £0.7125m in 2045/45 which is to be funded from the Towns Fund Grant. c) Rushden Library Improvements - £50k in 2023/24 which is to be funded from S106 contributions. d) Wellingborough Library Improvements - £29.3k in 2023/24 which is to be funded from S106 contributions. e) Family Hubs – £197k; £130k in 2023/24 and £67k in 2024/25 which is to be funded from the Family Hubs Transformation Grant. f) Potholes Repair Funding - £1.494m in 2023/24 which is to be funded from Department for Transport (DfT) Grant. That Executive note the following changes to the capital programme (approved at Council 30 th March): a. Isham Bypass - £1.573m in 2022/23 which is to be funded from a virement from the Integrated Transport Block Funding (2021/22 £0.742m; 2022/23 £0.558m) and £0.273m additional funding from s.278 contributions. Reasons for Recommendations: These are set out in greater detail within section 5 of the report, but can be summarised as: · To support the statutory delivery of school places and SEND school places across North Northamptonshire. · To support the Corby Town Deal · To support the provision of library services within North Northamptonshire · To support the delivery of the Northamptonshire Transportation Plan Alternative Options Considered: · As all the schemes in this report are grant funded/S106 funded, the use of the funding is in line with the agreements, so there are no alternative option proposed in this report. · Where individual schemes are over £500k, individual reports are presented elsewhere on the agenda/ have already been reported through to The Executive that set out the wider options that were considered before reaching the proposed schemes identified for grant funding.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update 2023/24Report 145 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Capital Programme Update 2023/24This decision
  2. General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030Approved
  3. Capital Programme Update 2025/26Noted
  4. Capital Programme Update 2025/26Approved
  5. Capital Programme Report 2025-2029Approved
  6. Capital Programme Update 2024/25Approved

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open