ItemC/261

Resolved

- a) That approval be given to the funding for the following changes to the capital programme: i) Phase 2 Refugee Resettlement Scheme – approve a budget in 2023/24 of £3.298m for phase 2 of the Refugee Resettlement Scheme funded through £1.298m from the Local Authority Housing Grant and a virement of £2m from the Housing and Homelessness prevention capital programme to the Resettlement capital programme to meet the match funding requirement for the grant. ii) Environmental Services ground maintenance equipment – approve a budget in 2023/24 of £445k for the replacement of grounds maintenance equipment funding from borrowing. b) Approval be given to the funding for the following changes to the revenue budget: i) Education Case Management System (ECMS) – approve a revenue budget of £1.362m in 2023/24 for the procurement and one-off implementation costs of a new ECMS funded through use of the Transformation Reserve, and approve the inclusion of ongoing revenue costs of £131k in 2024/25 and £142.5k in 2025/26 into the MTFP. Reasons for Recommendations: These are set out in greater detail within section 5 of the report, but can be summarised as: i) To support the housing provision in North Northamptonshire; ii) To support the achievement of corporate plan objectives; and iii) To improve service provision in relation to children, young people, parents and carers Alternative Options Considered: i) Alternative options in relation to the Phase 2 Refugee Resettlement Scheme can be summarised as follows:– · Do nothing – if the Council does not participate in this programme, it will not receive the funding allocation and the challenge of finding onward settled accommodation for refugees will remain;. · Commit to delivering a smaller number of homes – whilst this may be easier to achieve, the government grant allocation will reduce proportionately and less homes will be acquired into our temporary accommodation stock. Ultimately fewer additional homes will be available to the Council to use as affordable housing for our residents in the longer term. ii) Alternative options in relation to Environmental Services Grounds Maintenance Equipment can be summarised as follows:- · External grants were explored but are not available for plant equipment. The option of leasing new equipment was considered, but not deemed to represent value for money and therefore borrowing is the most cost-effective funding source. The other alternative option would be to not approve this scheme. However, this would have an adverse impact on meeting service needs and the achievement of NNC’s corporate objectives. iii) Alternative options considered for the ECMS can be summarised as follows:- · Do nothing; · Apply for a variation with the current supplier, subject to this option being available under the current contract and such modification satisfying the Public Contracts Regulations 2015;Reprocure the current system through a direct award; or Build a bespoke system for the Education Service. More detail in relation to alternative options considered by the Executive in respect of the three schemes are set out in the reports presented on 12th July and 17th August 2023, as referenced in Section ... C/261 - a) That approval be given to the funding for the following changes to the capital programme: i) Phase 2 Refugee Resettlement Scheme – approve a budget in 2023/24 of £3.298m for phase 2 of the Refugee Resettlement Scheme funded through £1.298m from the Local Authority Housing Grant and a virement of £2m from the Housing and Homelessness prevention capital programme to the Resettlement capital programme to meet the match funding requirement for the grant. ii) Environmental Services ground maintenance equipment – approve a budget in 2023/24 of £445k for the replacement of grounds maintenance equipment funding from borrowing. b) Approval be given to the funding for the following changes to the revenue budget: i) Education Case Management System (ECMS) – approve a revenue budget of £1.362m in 2023/24 for the procurement and one-off implementation costs of a new ECMS funded through use of the Transformation Reserve, and approve the inclusion of ongoing revenue costs of £131k in 2024/25 and £142.5k in 2025/26 into the MTFP. Reasons for Recommendations: These are set out in greater detail within section 5 of the report, but can be summarised as: i) To support the housing provision in North Northamptonshire; ii) To support the achievement of corporate plan objectives; and iii) To improve service provision in relation to children, young people, parents and carers Alternative Options Considered: i) Alternative options in relation to the Phase 2 Refugee Resettlement Scheme can be summarised as follows:– · Do nothing – if the Council does not participate in this programme, it will not receive the funding allocation and the challenge of finding onward settled accommodation for refugees will remain;. · Commit to delivering a smaller number of homes – whilst this may be easier to achieve, the government grant allocation will reduce proportionately and less homes will be acquired into our temporary accommodation stock. Ultimately fewer additional homes will be available to the Council to use as affordable housing for our residents in the longer term. ii) Alternative options in relation to Environmental Services Grounds Maintenance Equipment can be summarised as follows:- · External grants were explored but are not available for plant equipment. The option of leasing new equipment ... view the full minutes text for item C/261
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Revenue Budget Update 2023/24Report 150 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Capital Programme and Revenue Budget Update 2023/24This decision
  2. General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030Approved
  3. Capital Programme Update 2025/26Noted
  4. Capital Programme Update 2025/26Approved
  5. Capital Programme Report 2025-2029Approved
  6. Capital Programme Update 2024/25Approved

More from North Northamptonshire Council

All decisions
MeetingDecisionOutcome
19 Feb 2026 Chair's AnnouncementsRESOLVED That the Guillotine (Procedure Rule 10) be suspended until no later than 4:00 p.m. Decided Open
19 Feb 2026 Political Balance on Council CommitteesRESOLVED That Council approved the changes to political balance set out in Appendix A, inclusive of the revised alloc... Approved Open
19 Feb 2026 General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030RESOLVED That Council approved: a) The 2026/27 Revenue Budget which includes: i) a net revenue budget of £891.3m (£45... Approved Open
19 Feb 2026 Housing Revenue Account (HRA) Final Budget 2026-27 and Medium-Term Financial PlanRESOLVED That Council approved: a) The 2026/27 Housing Revenue Account Budget as set out in Appendix A of the report ... Approved Open
19 Feb 2026 Treasury Management StrategyRESOLVED That Council approves the Authorised Borrowing Limit for External Debt of £799.664m and the Operational Boun... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies