Kettering Library Roof Replacement Capital Project

Approved Executive 1 paper

Executive approved this item on Thursday 16 November 2023. Below is the council's own wording, with the papers it was decided on.

Item536

Resolved

RESOLVED KEY DECISION That the Executive: a) Recommended to Council the approval of the budget of £6,807,000 to be added to the Capital Programme to fulfil the Executive’s longstanding commitment to replace the Kettering Library roof and to commit to repair the roof of the Art Gallery. b) Delegated authority to the Executive Member for Sport, Leisure, Culture and Tourism, in consultation with the Director of Public Health and the Director of Place and Economy, to procure the necessary works to replace the Kettering Library roof and undertake any actions required to deliver the project within the approved financial envelope Reasons for Recommendations: · The library building is Grade II listed and it is the responsibility of the Council as the owner to maintain it. Further, the Council has various statutory enforcement powers to require the owners of listed buildings to keep listed buildings in a good state of repair. It is therefore important that the Council demonstratesits preparedness to tackle the condition of listed buildings. · If the building is not made watertight as soon as practicable there is a risk that further water ingress will compromise the structure of the building and cause damage to the internal fabric, library stock and equipment. · To enable the Council to continue to deliver its full statutory library functions within Kettering town centre. · Over the weekend 13 th /14th October 2023 further heavy rain caused the ceiling to collapse in a section to the right of the side doors of the library. This resulted in the library having to close whilst urgent remedial works and a clear up are undertaken and assessment is made as to the safety risks in re-opening the library to staff and the public. The frequency and likelihood of this re-occurring increases whilst the building remains exposed to the elements with the roof in the condition it is in. Options are now having to be considered to relocate the library until the building is watertight. · Cornerstone cannot open in its entirety until the building is watertight, due to water ingress into the new space on the ground floor , where the old roof meets the new. Inability to fully open Cornerstone compromises the Council’s ability to comply with the funding agreement in place with SEMLEP and exposes the Council to a risk that some of this funding will be clawed-back. The Council submits twice yearly monitoring reports to SEMLEP and so they are aware of the current challenges and have been supportive to date but want to see Cornerstone fully open as soon as practicable. · The Gallery has a revenue cost to the Council and the intention, should Cornerstone be open, is for the new spaces to generate an income that will offset some of these costs. · Whilst Cornerstone remains closed the Gallery Collection is not accessible to the public. Alternative Options Considered: · Not undertaking the work to replace the library roof This would result in the permanent closure of the library building and the need to permanently relocate ...
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Kettering Library Roof Replacement Capital ProjectReport 182 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Kettering Library Roof Replacement Capital ProjectThis decision
  2. Kettering Alfred East Art Gallery, Library and Museum Project Update (Cornerstone)Noted
  3. Procurement of Catering Services at Kettering Library and Alfred East Gallery (GLaM project)Decided

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies