North Northamptonshire Council
Executive, Thursday 15 February 2024 at 10.00am

Capital Programme Update 2023/24

Approved Executive 1 paper

Executive approved this item on Thursday 15 February 2024. Below is the council's own wording, with the papers it was decided on.

Item594

Resolved

RESOLVED KEY DECISION That the Executive: i) Approved the following changes into the capital programme: a. Manor School, Raunds SEND Provision - budget approval for £145k in 2024/25, to be funded from external grant. b. Corby Business Academy SEND Provision - budget approval for £544k, £2k in 2023/24, £542k in 2024/25, to be funded from external grant. c. End User Devices – virement of £441k from completed existing ICT schemes to End User Devices scheme, funding to remain as approved from capital receipts. d. Community Orchards – budget approval for 16K in 2023/24, to be funded from external grant. e. Mirco Woodlands – budget approval for £27.7k in 2023/24, to be funded from external grant. Reasons for Recommendations: These are set out in greater detail within section 5 of the report, but can be summarised as helping to meet the Council’s corporate plan objectives: - Active, fulfilled lives - Safe and Thriving Places - Green sustainable environment - Connected Communities Alternative Options Considered: · For those schemes which are grant funded, they are undertaken in accordance with the requirements of the grant conditions and, therefore, there is no alternative option proposed in this report. · The budget virement in support of the ICT equipment could have been released, however, the replacement of end user devices is an important element of ensuring that the Council has the appropriate equipment to support and deliver services and further investment is required in this area. · Where individual schemes are over £0.5m, separate reports are included elsewhere on this agenda, and these set out the wider options that were considered before reaching the proposals put forward.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Update 2023/24Report 133 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Northamptonshire

Search all
  1. Capital Programme Update 2023/24This decision
  2. General Fund Final Budget 2026-27, Medium-Term Financial Plan and Capital Programme 2026 to 2030Approved
  3. Capital Programme Update 2025/26Noted
  4. Capital Programme Update 2025/26Approved
  5. Capital Programme Report 2025-2029Approved
  6. Capital Programme Update 2024/25Approved

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies