Green Hill Solar Farm

Refused Executive 6 papers

Executive refused this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.

Item757

Resolved

RESOLVED KEY DECISION That the Executive: a) Endorsed the Regulation 11 Notice to submit a draft statutory consultation response on the Preliminary Environmental Impact Report (PEIR) in regard to the proposed Green Hill Solar Farm. b) Delegated authority to the Executive Director of Place and Economy, in consultation with the Executive Member for Growth and Regeneration, to respond to consultations and engagement from the developer and the Planning Inspectorate (including the Examining Authority) during the following Development Consent Order stages: Pre-application; Acceptance; Pre-Examination; Examination; and Post-Examination. c) Delegated authority to the Executive Director of Place and Economy to deal with post-decision matters (if development consent is granted) including matters such as determination of applications under the Development Consent Order consenting regime and enforcement in respect of any Development Consent Order granted by the Secretary of State. Reason for Recommendations – · To adhere to the guidance set down by the Planning Inspectorate to ensure adequate delegations are in place to enable the Council to represent the interests of North Northamptonshire Council as ‘Host Authority’ and participate in the Development Consent Order stages within the tight formal timeframes. Alternative Options Considered – · It has been considered whether the authority of the Executive should be sought at each of the different stages of the Development Consent Order process. This has been rejected due to the need to meet statutory timescales and the risk that the impacts of the development on North Northamptonshire’s local communities would not be fully considered. · The Council could also decide not to respond further to the Development Consent Order process. This course of action is not recommended due to the risk that the impacts of the development on North Northamptonshire’s local communities would not be fully considered and any opportunity to secure mitigation for the impacts would be lost should consent be granted. Furthermore, this option is likely to be reputationally damaging to the Council, especially given its status as a ‘Statutory Consultee’ and ‘Host Authority’.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 66 KB Copy on its way
PDF
Appendix BAppendix B 293 KB Copy on its way
PDF
Appendix CAppendix C 205 KB Copy on its way
PDF
Appendix DAppendix D 18 MB Copy on its way
PDF
Appendix EAppendix E 4 MB Copy on its way
PDF
Green Hill Solar FarmReport 427 KB Copy on its way

At this meeting

Whole meeting

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open