CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Northamptonshire Council
Executive, Thursday 13 February 2025 at 10.00am

Government Funding to Support Economic Growth in 2025-26

Approved Executive 2 papers

Executive approved this item on Thursday 13 February 2025. Below is the council's own wording, with the papers it was decided on.

Item778

Resolved

RESOLVED KEY DECISION That the Executive: a) Welcomed the allocation to North Northamptonshire of £1,581,860 through the UK Shared Prosperity Funding and delegated approval to the Section 151 officer to sign the Memorandum of Understanding with Government to secure the funding. b) Agreed that the funding continues to be targeted in line with the submitted Investment Plan and approach as set out in paragraph 4.6. c) Supported the continuation of arrangements for the award of funding and related matters, with decisions delegated to the Executive Director of Place & Economy (Deputy Chief Executive) in consultation with the Executive Member for Growth & Regeneration, and alongside and through engagement with the UK Shared Prosperity Fund Panel, also comprising the Executive Members for Housing, Communities & Levelling Up and Rural Communities & Localism. d) Welcomed the new Connect to Work programme and move towards locally delivered employment support and agree that the Council develop a Local Delivery Plan for North Northamptonshire working alongside other principal local authorities in the South Midlands. e) Delegated authority to the Executive Director, Adults, Health Partnerships & Housing, in consultation with the Executive Member for Adults, Health & Wellbeing, to submit the Connect to Work Programme Local Delivery Plan to Government, and the Section 151 Officer authorise any related agreements to secure the funding and deliver the programme in this area. Reasons for Recommendations – The recommendations will ensure that: · The Council can take full advantage of the funding which has been allocated to the area through the UK Shared Prosperity Fund. This follows the decision by Government to extend the programme for a further year. · The Council can secure funding support through the Government’s new Connect to Work programme. This programme will help address barriers to employment and economic activity targeting people with physical, mental or other challenges. Alternative Options Considered – The Council could choose not to support either or both the UK Shared Prosperity Fund and Connect to Work (C2W) programme. However, this approach would result in lost funding and associated opportunities to communities, residents, businesses, and other stakeholders in the area. An alternative approach to the C2W programme could involve developing a joint Local Delivery Plan, but this would inevitably slow progress, add further complexity, and could limit the ability to target funding on local priorities.
Word for word from the decision North Northamptonshire published for this meeting. Source: northnorthants.moderngov.co.uk

Follow this further

Built from North Northamptonshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 257 KB Copy on its way
PDF
Government Funding to Support Economic Growth in 2025-26Report 204 KB Copy on its way

More from North Northamptonshire Executive

All decisions
MeetingDecisionOutcome
20 Jan 2026 Minutes of the meeting held on 16th December 2025RESOLVED that the Executive agreed the minutes of the meeting held on 16 th December 2025 as a true and accurate reco... Agreed Open
20 Jan 2026 Post-Financial Settlement General Fund Draft Budget Update Report 2026-27RESOLVED KEY DECISION That the Executive: i) Noted the funding changes to the draft budget as set out in Table 1 of t... Noted Open
20 Jan 2026 Network Management PlanRESOLVED KEY DECISION That the Executive: i) Approved the Highway Network Management Plan as shown at Appendix A to t... Approved Open
20 Jan 2026 Procurement of Waste and Recycling ContainersRESOLVED KEY DECISION That the Executive: i) Approved the recommendation to arrange a four-year agreement for the sup... Approved Open
20 Jan 2026 Saunders Close Kettering & Lawrence Factory Desborough Capital WorksRESOLVED KEY DECISION That the Executive: i) Approved the commencement of the procurement process to fully demolish t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies