CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Tyneside Council
Planning Committee, Tuesday 4 August 2020 at 10.00am

20/00632/OUT Management Suite, Royal Quays Outlet Centre, Coble Dene, North Shields, Tyne And Wear

Agreed Planning 1 paper

Planning Committee agreed this item on Tuesday 4 August 2020. Below is the council's own wording, with the papers it was decided on.

ItemPQ91/20

Resolved

Resolved that (1) the Committee indicates that it is minded to grant the application subject to the conditions set out in the planning officer’s report and addendum and to the completion of an Agreement under Section 106 of the Town and Country Planning act 1990 and the addition, omission or amendment of any other conditions considered necessary; and (2) the Head of Housing, Environment and Leisure be granted delegated authority to determine the application following the completion of the Section 106 Legal Agreement to secure the following: Ecology and Biodiversity: £6,825 Employment and Training: 0.5% of the total capital costs and/or apprenticeship opportunities within the construction and end user phase. Coastal Mitigation: £153 per unit towards the Coastal Mitigation Scheme (Reasons for decision: The Committee concluded that, having regard to the relevant policies contained in the Council’s Local Plan 2017 and National Planning Policy Framework, the proposed development was acceptable in terms of the principle of development, including its impact on surrounding occupiers and on the character and appearance of the site and its surroundings, its impact on car parking and access and the impact on trees and ecology.)
Word for word from the decision North Tyneside published for this meeting. Source: democracy.northtyneside.gov.uk

Follow this further

Built from North Tyneside's papers

What the report saysPro

Report to Planning Committee

Item No: 4 Application 20/00632/OUT Author: Rebecca Andison No: Date valid: 28 May 2020 : 0191 643 6321 Target 27 August 2020 Ward: Riverside decision date:

Application type: outline planning application

Location: Management Suite, Royal Quays Outlet Centre, Coble Dene, North Shields, Tyne And Wear

Proposal: Outline application with all matters reserved - new hotel development comprising approximately 70 bed spaces and associated car parking

Applicant: WD Chatham Ltd, [name removed] 9-10 Staple Inn London WC17 7QH

Agent: Covell Matthews Architects Ltd, [name removed] 6 Manor Place Edinburgh EH3 7DD

RECOMMENDATION: Minded to grant legal agreement req.

INFORMATION

1.0Summary Of Key Issues & Conclusions

1.0Main Issues 1.1 The main issues for Members to consider are: - whether the principle of the proposal is acceptable; - the impact on surrounding occupiers; - the impact on the character and appearance of the site and its surroundings; - whether there is sufficient car parking and access provided; and - the impact on trees and ecology.

2.0Description of the Site 2.1 The application relates to part of the car park which serves the Royal Quays Outlet shopping centre.

2.2The site is located adjacent to Coble Dene, immediately to the east of an inflatable theme park and to the north of an existing Premier Inn Hotel. To the south east is a public house (Brewer’s Fare). The area to the north contains a variety of uses, including a water park, bowling alley and residential properties. The International Ferry Terminal and Royal Quays Marina are located a short distance to the east, at the end of Coble Dene.

INIT 3.0 Description of the proposed development 3.1 This application seeks outline planning permission for the development of a hotel and associated car parking. All matters are reserved for subsequent approval.

3.2The hotel would be 3-storey in height and contain approximately 70no. bedrooms.

4.0Relevant Planning History 4.1 The Royal Quays Centre has an extensive planning history dating back to 2000 when planning permission was granted for the refurbishment of the Royal Quays development under the following application:

00/00328/FUL - Proposed refurbishment to include some change of use, demolition and rebuilding, provision of new and extended retail units, new canopies, amended car parking – Permitted 15.09.2000

4.2The most recent applications are listed below:

20/00523/FUL - Proposed partial change of use of existing A1 Factory Outlet Shopping Centre to A1 Factory Outlet/B1/B8 Industrial. Alterations to existing service arrangements to suit new use – Permitted 08.07.2020

16/01263/AMEND – Non Material Amendment of planning approval 15/01567/FUL - Repositioning of main entrance and service access, three new emergency accesses and steps, changes to ground level and height, loss of two car parking spaces and altered hard landscaping layout – Permitted 28.09.2016

15/01567/FUL - Erection of a trampoline hall – Permitted 17.02.2016

14/01961/FUL - Proposed temporary garden centre (A1 Use) to be part of the existing Royal Quays Outlet Shopping Centre – Permitted 10.03.2015

5.0Development Plan 5.1 North Tyneside Local Plan 2017

6.0Government Policy 6.1 National Planning Policy Framework (February 2019)

6.2Planning Practice Guidance (As amended)

6.3Planning applications must be determined in accordance with the development plan unless material considerations indicate otherwise. The NPPF is a material consideration in the determination of all applications. It requires LPAs to apply a presumption in favour of sustainable development in determining development proposals. Due weight should still be attached to Development Plan policies according to the degree to which any policy is consistent with the NPPF.

INIT PLANNING OFFICERS REPORT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20/00632/OUT Management Suite, Royal Quays Outlet Centre, Coble Dene, North Shields, Tyne And WearReport 264 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
KB
Councillor Ken BarrieCommittee Member, present
TB
Councillor Trish BradyDeputy Chair, present
BB
Councillor Brian BurdisCommittee Member, absent
LD
Councillor Linda DarkeCommittee Member, present
JD
Julia DawsonCouncil Staff, expected
SG
Councillor Sandra GrahamCommittee Member, present
MG
Councillor Muriel GreenCommittee Member, present
CJ
Councillor Carl JohnsonCommittee Member, present as substitute
FL
Councillor Frank LottChair, present
PR
Councillor Paul RichardsonCommittee Member, apologies, sent representative
WS
Councillor Willie SamuelCommittee Member, present
JS
Councillor John StirlingCommittee Member, absent

All 13 on the meeting page

More from North Tyneside Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 25/01299/FULM - Land At Former Tyne Brand Building, Tanners Bank, North Shields, Tyne And WearResolved that the application be permitted subject to the conditions set out in the report. Decided Open
19 Aug 2026 Land off Williams Park - Tree Preservation Order 2026RESOLVED that the land off Williams Park, Tree Preservation Order 2026 be confirmed without modification. Decided Open
10 Jun 2026 23/00480/OUT - Land Adjacent To, Killingworth Lane, Killingworth, Newcastle Upon TyneResolved that the application be permitted subject to the conditions set out in the report and a S106 legal agreement. Agreed Open
8 Apr 2026 25/00974/FUL - Land At Former 3 Park Drive Forest Hall Newcastle Upon TyneResolved that the application be deferred pending a site visit. Deferred Open
8 Apr 2026 26/00025/FUL - Central Lower Promenade Whitley Bay Tyne And Wearthat the application be permitted subject to the conditions set out in ... view the full minutes text for item PC101/25 Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies