Resolved that the report of the Overview, Scrutiny and Policy Development Committee on the in-depth review of the Authority’s Engie partnership be noted, and a detailed response to the recommendations be provided at a future Cabinet meeting, no later than August 2021. (Reason for decision – Cabinet has a statutory duty to respond to the Overview, Scrutiny and Policy Development Committee recommendations within two months of receiving them).
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
The purpose of this report is to present the findings of the Engie Sub-group who carried out an in-depth review of the Authority’s partner on behalf of the Overview, Scrutiny and Policy Development Committee.
The recommendations are set out in paragraph 1.5.4 below.
In accordance with section 9F of Part 1A of the Local Government Act 2000, Cabinet is required to provide a response to the recommendations of the Overview, Scrutiny and Policy Development Committee within two months. In providing this response Cabinet is asked to state whether or not it accepts each recommendation and the reasons for this decision. Cabinet must also indicate what action, if any, it proposes to take.
1.2Recommendation(s):
It is recommended that Cabinet consider and formulate a response to the recommendations presented to them as a result of the Overview, Scrutiny and Policy Development Committee’s study into the Engie Partnership.
1.3Forward Plan:
The report was included in the Forward Plan published in March 2021 under the heading “Matters arising from Overview, Scrutiny and Policy Development Committee and its sub- committees”.
1.4Council Plan and Policy Framework
The report relates to the following priority in the 2020/2024 Our North Tyneside Plan: Our Economy will:
be dynamic and more inclusive, which will ensure that all residents have a stake in our region’s future
1.5Information:
1.5.1 Background
1.5.2 Overview, Scrutiny & Policy Development Committee has a programme to undertake in- depth reviews into the out-sourced partnerships that deliver services on behalf of the Authority, with the aim to see if the Authority and its residents are receiving the service specified in the contracts. The Committee established the Engie Sub-group to undertake this work to gain a clearer understanding of the partnership and its operation.
1.5.3 Continuing the policy to encourage cross party/committee involvement in scrutiny, an invitation was made to all Non-Executive Members of the Council to be part of the sub- group and the sub-group met on 10 occasions, where it received information from senior lead officers of the Council and its Engie Partners for each of the contract workstreams.
1.5.4 The Sub-Group has made a total of 3 recommendations for Cabinet’s consideration:
1) In its benchmarking activity pay particular attention to the strategic aspects of service delivery of the partnership.
2) Following benchmarking testing, it believes if the Partner is not providing value for money it should consider amending the contract to assure best value and/or investigate all options to in-source parts/all services.
3) The group feels that as and when legally possible and at the best and earliest opportunity that these services should be returned and insourced to the local authority.
1.5.5 The full report and recommendations of the review is attached at Appendix 1
1.5.6 The Overview, Scrutiny and Policy Development Committee will receive the report on 14 June 2021 for approval for submission to Cabinet.
1.6Decision options:
The following decision options are available for consideration by Cabinet:
Option 1
Cabinet may accept the recommendation set out in paragraph 1.2 above
Option 2
Cabinet may not accept the recommendation set out in paragraph 1.2 above and provides a response to the Overview, Scrutiny and Policy Development Committee at the meeting. Option 3
Cabinet may accept part of the recommendation as set out in paragraph 1.2 above
Option 1 is the recommended option.
1.7Reasons for recommended option:
Cabinet has a statutory duty to respond to the Overview, Scrutiny and Policy Development Committee’s recommendations within 2 months of receiving them. Option 1 is recommended as this option allows Cabinet to consider and formulate a response to the recommendations
Appendices
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of...
Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.