Resolved that (1) the updated Our North Tyneside Council Plan, as set out in Appendix 1 of the report be approved, subject to consideration of any supplementary information received as a result of the ongoing engagement process; and (2) the Deputy Mayor be authorised to agree any final changes to the Our North Tyneside Plan in the light of any further responses received to consultation between the date of this Cabinet meeting and the end of the engagement process. (Reasons for decision: the content of the updated Council Plan has been informed by the findings of a comprehensive engagement approach delivered in line with the Covid-19 restrictions. Approval of the updated Council Plan will enable a report to be taken to full Council on 23 September 2021, in advance of the Council’s budget setting process beginning.)
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
This report seeks Cabinet’s approval of an updated Our North Tyneside Council Plan, in light of the findings from engagement with residents and other key stakeholders. This engagement is being undertaken in accordance with the approach agreed by Cabinet on 28 June 2021.
As the engagement process is not due to conclude until 15 August 2021, it may be necessary to provide supplementary information regarding the engagement findings following the publication of the Cabinet agenda for 2 August, and possibly following the meeting itself.
Recommendation
It is recommended that Cabinet approve the updated Our North Tyneside Council Plan as set out in Appendix 1, subject to consideration of feedback received throughout the engagement process.
1.3Forward Plan:
Twenty-eight days notice of this report has been given and it first appeared on the Forward Plan that was published on 25 June 2021.
1.4Council Plan and Policy Framework
This report sets out the proposed updated 2020-2024 Our North Tyneside Plan. The Council Plan is a ‘local choice’ plan under the Budget and Policy Framework as set out in the Council’s Constitution. 1.5 Information:
1.5.1 Background
1.5.2 The previous Our North Tyneside Council Plan 2020-2024 was approved by full Council on 18 February 2021. Following the Mayoral election on 6 May 2021 the Council Plan needed to be updated to reflect the policy priorities of the incoming administration. As per the Council’s Budget and Policy Framework, as set out in the Council Constitution, the Council Plan requires final approval by full Council.
1.5.3 At its meeting on 28 June 2021 Cabinet approved a plan for internal and external engagement on the initial proposals for an updated Council Plan (see Appendix 1). Engagement began on Friday 2 July 2021 and will continue until 15 August (including consideration by the Overview, Scrutiny and Policy Development Committee at its meeting on 7 July). Following Cabinet’s consideration of this report, and any supplementary information received, approval of the updated Council Plan will be sought from Council at its meeting on 23 September.
1.5.4 Our North Tyneside Council Plan 2021-24 Engagement
1.5.5 In accordance with the engagement plan agreed by Cabinet in June, the following has been undertaken:
publication of information about Cabinet’s initial Council Plan proposals from the end of June and throughout July. This has been achieved online via the Council’s website and at front line locations including the Community Conversation corners in the four Customer First Centres, where these have been available in line with Covid-19 restrictions. Feedback from residents and others is in the process of being gathered via a questionnaire either on-line or at these front-line locations (to date 165 responses have been received, the vast majority agreeing with the Council Plan proposals). This engagement process has been supported by communications activity via the media and social media to raise awareness of opportunities to take part;
the views of Overview, Scrutiny and Policy Development Committee were sought on 7 July and are outlined in Appendix 2.
in addition to the opportunity to respond to the questionnaire, engagement sessions have been offered to the following internal and external stakeholder groups:
o staff o businesses o schools o children and young people o trade unions o North Tyneside Strategic Partnership o older people o carers o Black, Asian and other Minority Ethnic Communities Task Force o low income households o groups representing people with protected characteristics under the Equality Act 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of...
Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.