Resolved
It was agreed that the presentation be noted
Environment Sub Committee (no longer active) agreed this item on Tuesday 10 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the presentation be noted
Surface Water Management in North Tyneside
Environment Sub-Committee 10 January 2023
Mark Newlands Highways & Infrastructure Manager Contents
• Background • Governance • Flooding Strategy • Work done to date • Partnership working • Measuring success – where we’ve got to • Next 10 years – what happens next Background Background Background
• June 2012 – Thunder Thursday • Task and finish group set up late 2012 • Flooding Strategy developed • £4.75m capital investment plus external grants • Implementation plan developed • Formal governance put in place • Numerous other activities e.g. flood wardens Governance
• North Tyneside Surface Water & Drainage Partnership established March 2013 • Brought together all partners and stakeholders • Chaired by lead cabinet member, supported by director • Directed and influenced work • Exchange of ideas and good practice • Brand / identity :
• Dissolved in January 2020 Flooding Strategy
Local Flood Risk Management Strategy
July 2014 Key Objectives 1) We will continue to encourage direct involvement in decision making through partnership working with key organisations and communities.
2) We will target resources where they have the greatest effect by continuation with a risk-based approach.
3) We will contribute to wider social, economic and environmental outcomes by encouraging sustainable multi benefit solutions for the management of local flood risk.
4) We will continue to encourage and support communities and local landowners to take action and contribute to the reduction of flood risk.
5) We will continue to ensure that emergency plans and responses to flood incidents are effective and that communities are able to respond properly to flood warnings.
6) We will ensure that our infrastructure is resilient to flooding and be ready to adapt to flooding change
7) We will provide further support to local residents to increase their own resilience to flooding Examples of Work Carried Out in North Tyneside Dudley – Green Lane Murton Village Phase 1 – Drainage Improvements • Improved drainage of highway
• Increased storage capacity of ditch
•Vehicle speeds reduced with new road hump Murton Village Property Level Protection (PLP) Woodburn Drive • Gabion basket flood barrier
• Surface water held within bridleway and channelled via a filter drain to a nearby culvert then out to sea Fairfield Green • 3 large dry storage basins connected by ditches • Controlled discharge Briar Vale •E Partnership Working Killingworth & Longbenton Sustainable Sewerage Project One Team Wild Life Trust Newcastle City Council Natural History Northumbrian Water Society
Land Owners Tyne Rivers Trust
Land Users North Tyneside Environment Council Agency Communities Developers
Business Schools
18 Measuring Success
• Around £25m flood schemes delivered • Hundreds of properties better protected • All priority sites dealt with • Emergency response plans improved • 2 new gully wagons and risk based approach • Residents better informed • Flood warden scheme in place Next 10 Years
• Continue work but on a smaller scale • Improve understanding of drainage issues through studies and modelling • Continue to seek external funding • Review performance of schemes built to date • Review and update Flooding Strategy in 2032 Thank you
Questions?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Flood Management Plan: Review of PerformanceReport | 7.8 MB | DownloadRead as text |
Follow Environment Sub Committee (no longer active) at North Tyneside and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jan 2023 | Fleet DecarbonisationIt was agreed that the presentation be noted. | Agreed | Open |
| 12 Jul 2022 | Overview of the Environment DirectorateIt was agreed that the presentation be received | Agreed | Open |
| 12 Jul 2022 | Draft Carbon Net Zero Action PlanIt was agreed that the presentation be received | Agreed | Open |
| 12 Jul 2022 | Work Programme 2022/23Resolved that (1) the above topics be included in the Sub-committee’s work programme for 2022/23; and (2) the Chair a... | Decided | Open |
| 11 Jan 2022 | Working towards a Net-Zero Carbon FutureResolved that (1) the report be noted; (2) Members views on the procurement strategy be sent direct to the officer; (... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.