To: Secure Sub Author: Richard Brook, Housing Committee Growth Manager Date: 25 March 2024
Title of Briefing: Affordable Homes Programme Update Report
1. Executive Summary The Our North Tyneside Plan was approved at full Council on 23 September 2021 and included a target of delivering 5,000 affordable homes and a commitment to reduce the number of derelict properties in the borough. To meet this ambitious target, Cabinet approved a two-phased delivery approach to the Affordable Homes Programme (AHP) on 21 February 2022.
Phase one of the AHP will see 4,000 affordable homes delivered by 2032 and an indicative programme for delivery is provided in Appendix A. This Phase will be delivered across several workstreams including directly delivered homes by the Authority, tackling derelict properties, and working in partnership with Aurora Affordable Homes and Registered Providers.
This Report provides the sub-committee with an update on the overall progress to deliver 5,000 affordable homes and highlight the work completed in 2023/24.
2. Information
2.1AHP Progress Overview The Affordable Homes Programme (AHP) was approved by Cabinet on the 14 May 2013 and by the end of 2023-2024 will have delivered nearly 2,300 new affordable homes including over 600 new council homes in 10 years. This constitutes a 182% improvement on the ten years prior to the programme starting.
www.northtyneside.gov.uk Briefing note
The Cabinet also approved a new five-year Housing Strategy on the 27 March 2023 that outlined plans to Build a Better North Tyneside. To meet the ambitious target of delivering 5,000 affordable homes, Cabinet, in February 2022, approved a two-phase approach to delivering the AHP. This approach included firm plans for the delivery of Phase One that will achieve the delivery of 4,000 homes by 2032 and identified workstreams that would be explored to deliver the additional 1,000 homes in Phase Two.
2.22023/24 Overview The Affordable Homes Programme has delivered 105 affordable homes in 2023-24 and is forecasting to deliver a further 11 homes in Q4 bringing the total to 116. This figure is below the planned 187 as a result in a significant slowdown of activity by developers on the larger sites. Construction has started on the majority of the 71 homes that will not be delivered by April 2024, and we expect these to be delivered in 2024-25. A list of affordable homes delivered in 2023-24 can be found in Appendix A.
3. 2023-24 Programme Detail
3.1New Council Housing The Authority has continued to prioritise building new homes and has undertaken the following work in 2023/24:
Blackhill Avenue & Belshill Close, Battle Hill – The second phase of HUSK properties at underused garage sites in Blackhill Avenue and Bellshill Close, Battle Hill are now complete with nine new affordable bungalows developed.
Conversion of recreation rooms – Work is ongoing converting six former Recreation Rooms. Works on bungalows at Richmond Gardens, Lynholm Grove, and Holystone Drive have now been completed. The remaining properties at Forest Hall Drive, Elizabeth Drive, and Morpeth Avenue will be complete in 2024/25.
Acquiring Homes for temporary accommodation – Two homes have been acquired for the use of temporary accommodation for people presenting as homeless. The homes are managed within the Housing Revenue Account and are used as dispersed properties.
Brownfield Housing Fund - The Authority has successfully bid for £1.4m of Brownfield Housing Funding to unlock 67 affordable new homes in Wallsend and Longbenton. The money will be used to remediate land on three derelict sites that have been attracting Briefing note
anti-social behaviour. Sites of the former Rosehill Social Club and Parkside House were purchased with plans to demolish the existing buildings in progress.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Affordable Homes Programme UpdateReport | 96 KB | DownloadRead as text |
Follow Secure Sub-Committee at North Tyneside and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2026 | Minutes of the Previous MeetingResolved that the minutes of the previous meeting held on 13 January 2026 be approved and signed by the Chair. | Approved | Open |
| 13 Jan 2026 | Minutes of the Previous MeetingResolved that the minutes of the previous meeting held on 18 November 2025 be approved and signed by the Chair. | Approved | Open |
| 18 Nov 2025 | Minutes of the Previous MeetingResolved that the minutes of the previous meeting held on 23 September 2025 be approved and signed by the Chair, subj... | Approved | Open |
| 23 Sep 2025 | Minutes of the Previous MeetingResolved that the minutes of the previous meeting held on 8 July 2025 be approved and signed by the Chair subject to ... | Approved | Open |
| 8 Jul 2025 | Minutes of the Previous MeetingResolved that the minutes of the previous meeting held on 10 March 2025 be approved and signed by the Chair. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.