It was agreed that while this was a factor, the issue of preference and aesthetics of multiple residents was potentially a difficult one to manage and would need to be considered. Risk Assessments were still occurring, with a Highways Inspector assessing all works. Officers stated that with the Service only recently having returned that not all streets had been evaluated yet in terms of necessary works, footfall, inspection rotas, styles and appropriateness of types of trees and risk. Officers stated that dealing with the issues of larger trucks occasionally going up onto pavements was still being explored and a cost effective solution rather than repeat visits was the aim. Suggestions were made by members of bollard placement and wider consultation with businesses, and officers confirmed that these were options available to them and had been previously employed where appropriate. Officers stated that investigations were still ongoing into the best material and ways to repair pavements including the viability of concrete bases. The Head of Highways and Transportation stated that traffic and transport plans for each ward were hoped to be a strong tool in preparation and awareness of issues. The committee is keen to see how the pilot progresses but asks that the views of pavement users, business and residents are obtained and taken into consideration.
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
The purpose of this report is to highlight issues relating to the maintenance of flagged footways in areas of frequent vehicle over-riding and around trees. It considers the types of treatment that could be used to address these defects.
Recommendations
That Green Sub-Committee is invited to note the information provided and recommend to Cabinet members a trial of alternative footway treatments detailed in this report to address vehicle over-riding/pavement parking and the impact that trees have on flagged footways. Following a 12-month trial a further report is prepared for consideration to detail the impact of the trials on the highway network.
3. Information
Historically, footways have been constructed using paving flagstones on a bed of sand and North Tyneside, similar to all other local authorities have a significant number of flagged footways. New footways in North Tyneside are constructed in tarmac, which is a much more resilient material that is less susceptible to damage from vehicle over-riding compared to a flagged construction.
Similar to many other LA’s the Council has a policy of replacing life expired flagged footways with flexible construction during programmed footway renewals because of the superior strength and resilient characteristics of flexible construction, and its ability to withstand vehicle loading.
Given the volume of existing flagged footway stock, this means that it will be many years before all such footways are replaced with a flexible surface. The existing stock must be maintained to the appropriate standard in the interim considering vehicle parking on the pavement and over-riding by larger vehicles, and the impact tree roots have on pavements.
The policy for reactive maintenance in flagged footways is to renew like for like, i.e. if an actionable defect is identified in a flagged footway, it is repaired using replacement flags. In most locations, this policy is reasonably effective and the repairs are successfully delivered without issue. However, in areas of flagged footways with frequent vehicle over-riding and surrounding trees it is difficult to successfully replace like for like.
The problem does not lie in the quality of the repair on the day, it lies in the nature of the location. Areas with frequent over-riding are frequently damaged soon if not immediately after repair and whilst the situation is not quite as immediate with trees, the tree roots are constantly growing and soon cause the return of trip hazards. Tree roots also cause another problem with like for like repairs as it is necessary to grind tree roots in order to relay flags safely. This activity damages the trees and significantly increases the risk of the trees uprooting.
3.2Areas of Frequent Vehicle Over-riding
Areas with frequent vehicle overriding, such as shopping areas, are traditionally protected by bollards. But it is prevalent in some residential areas where larger vehicles such as those delivering goods, are regularly over-riding or park on the footway. Whilst this activity is undesirable, in many cases it is necessary because lots of residential streets are very narrow and if vehicles were restricted to parking on the carriageway, the street would be obstructed, particularly for service and emergency services vehicles. Consequently, it would be impractical to either install bollards or to try to prevent pavement parking via enforcement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.