RESOLVED to: 1. Agree to introduce planning obligation monitoring fees to support the costs of the Authority monitoring and reporting on planning obligations imposed on developers and others by way of agreements entered into under section 106 of the Town and Country Planning Act 1990 at the levels set out in paragraph 1.5.14 of this report with such fees taking effect from 1 September 2025; 2. Agree to introduce Biodiversity Net Gain monitoring fees to support the costs of the Authority monitoring and reporting on developers and others by way of agreement entered into under section 106 of the Town and Country Planning Act 1990 at the levels set with such fees taking effect from 1 September 2025; and 3. Authorise the Director of Regeneration and Economic Development in consultation with the Deputy Mayor, Director of Resources and Head of Law to review and update the planning obligation monitoring fees and Biodiversity Net Gain monitoring fees annually as appropriate. Reason for the DECISION: The Authority has the ability to introduce a fee for the monitoring work and to do so will enable a more proactive approach to monitoring.
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
This report seeks Cabinet’s agreement to the introduction of section 106 planning obligation monitoring fees from 1 September 2025. Agreement is also sought for the introduction of monitoring fees relating specifically to the need for the Authority to monitor Biodiversity Net Gain (BNG) obligations placed on developers. Subject to agreement, such fees will also be introduced on 1 September 2025.
It is proposed to introduce a fee to cover the costs of monitoring compliance with planning obligations which are imposed on development proposals via legally binding agreements made between the Authority and developers under section 106 of the Town and Country Planning Act 1990. Such agreements are commonly known as “section 106 agreements”. These agreements, amongst other things, include obligations relating to the requirements for the mandatory 10% BNG obligations placed on developers with the introduction of Schedule 7A of the Town and Country Planning Act 1990 which came into effect in 2024. Section 106 Agreements are made by deed and permit the Authority, as the Local Planning Authority (LPA) to agree with a landowner or developer for them to provide something as part of the planning consent, which can be a financial payment, or a restriction on the use of a development. Section 106 agreements and the planning obligations within them ensure that developers contribute towards the infrastructure that is required to make a development acceptable in planning terms.
The Authority applies its Community Infrastructure Levy (CIL) in relation to many developments, but Section 106 agreements remain commonplace, and there remains significant requirements on the Authority in terms of the on- going monitoring of compliance with obligations forming part of section 106 agreements.
The Authority, as a Local Planning Authority (LPA), can charge a monitoring fee through planning obligations to cover the cost of monitoring and reporting on the delivery of section 106 obligations. Monitoring fees can be used to monitor and report on any type of planning obligation, for the lifetime of that obligation. Fees could be a fixed percentage of the total value of the planning obligations or individual obligation; or could be a fixed monetary amount per planning obligation. In all cases, monitoring fees must be proportionate and reasonable and reflect the actual cost of monitoring.
It is proposed that the monitoring fees will be applied per planning obligation. The fees, if agreed, will be periodically reviewed to ensure the administrative costs associated with the monitoring and managing of developer contributions are covered by the fees.
Recommendations
It is recommended that Cabinet;
(1) Agree to introduce planning obligation monitoring fees to support the costs of the Authority monitoring and reporting on planning obligations imposed on developers and others by way of agreements entered into under section 106 of the Town and Country Planning Act 1990 at the levels set out in paragraph 1.5.14 of this report with such fees taking effect from 1 September 2025, other than in current cases where developers have already indicated a willingness to pay a monitoring fee; (2) Agree to introduce Biodiversity Net Gain monitoring fees to support the costs of the Authority monitoring and reporting on developers and others by way of agreement entered into under section 106 of the Town and Country Planning Act 1990 at the levels set out in paragraph 1.5.16 of this report with such fees taking effect from 1 September 2025, other than in current cases where developers have already indicated a willingness to pay a monitoring fee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of...
Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.