Corporate Risk Management Summary Report

Decided Executive 2 papers

AI summaryCabinet noted 13 corporate risks, including a new one on climate change adaptation, as part of the twice yearly senior review.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOption 1 recommended and approved
MoneyNot stated
What happens nextContinuous review by risk ownersFormal SLT and Cabinet review twice a year
Who it affectsAll council service areasRisks cover all five council plan priorities

What was decided

Cabinet considered and noted the 13 corporate risks set out in the appended Corporate Risk Management Report. Report P7

Cabinet may ask the Head of Assurance and Risk to make changes to the corporate risks if needed. Report P8

Why

The corporate risks have been subject to robust review and challenge as part of the Authority's corporate risk management process. Report P32

The process is designed to give assurance that risks and opportunities are being identified and managed appropriately. Report P32, P54

What happens next

Risks will continue to be kept under continuous review by their named risk owners. Report P1, P16

The Senior Leadership Team and Cabinet will formally review and challenge corporate risks twice a year. Report P3, P18, P19

The Head of Assurance and Risk will update the corporate risks if Cabinet asks for changes. Report P8

Options considered

  • Chosen: Cabinet agrees the recommendation to note the corporate risks. Risks have been subject to robust review and challenge through the corporate risk management process. Report P26, P27, P29, P32
  • Rejected: Cabinet does not agree the recommendation Report P28

Implications

  • Legal: Supports compliance with Section 151 of the Local Government Act 1972, the CIPFA Statement on the role of the Chief Finance Officer, and the Accounts and Audit Regulations 2015. Report P44, P45, P46
  • Risk: 13 corporate risks identified, covering information governance, health and safety, pandemic flu, finance, workforce, health inequalities, Carbon Net Zero 2030, adult social care, SEND, children's social care, cyber security, Prevent duty, and climate change adaptation. Report P20, P21
  • Climate: A new corporate risk on adaptation to climate change and extreme weather events has been added, drawn from the 2024 DEFRA Adaption Reporting Pilot. Report P22
  • Financial: No direct financial implications; any costs are met from existing budgets or via the financial planning and budget monitoring process. Report P41
  • Equalities: No equalities, diversity, human rights, crime and disorder, or environment and sustainability implications arise directly from this report. Report P51, P53, P56, P58

Who and where

  • All North Tyneside Council services covered by the five Our North Tyneside Plan priorities Report P12, P13, P14
  • Risk owners, who are Senior Leadership Team members and Cabinet Members with relevant portfolios Report P3, P17, P48

Timeline

  • 29 August 2025: Report first appeared on the Forward Plan, with 28 days' notice given. Report P10
  • 3 September 2025: Senior Leadership Team formally reviewed the corporate risks under the Risk Management Framework. Report P4, P18
  • 2025-10-20: Cabinet considered and noted the corporate risks.

Plain English for the jargon

  • SLT: Senior Leadership Team, the most senior officers in the Authority.
  • CFO: Chief Finance Officer, appointed under Section 151 of the Local Government Act 1972.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, the professional body for public finance.
  • SEND: Special Education Needs and Disability.
  • DEFRA: Department for Environment, Food and Rural Affairs, referenced in connection with the 2024 Adaption Reporting Pilot.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB50/25

Resolved

RESOLVED to: 1. Consider and comment upon the corporate risks set out in the Corporate Risk Management Report . Reasons for the DECISION: Corporate risks have been subject to robust review and challenge as part of the Authority’s corporate risk management process which is designed to provide assurance that corporate risks and opportunities are being identified and appropriately managed.
Word for word from the decision North Tyneside published for this meeting. Source: democracy.northtyneside.gov.uk

Follow this further

Built from North Tyneside's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1.1 The Authority’s Risk Management Framework sets out its systematic approach to the process of identifying, assessing and mitigating risks, including corporate risks. Risk management within the Authority is dynamic and all risk are kept under constant review by risk owners.

1.1.2 The corporate risks identified in this report are not unique to North Tyneside Council and similar risks can be found on local authority risk registers throughout the country. The Authority are also aware of the risks identified within the Government’s National Risk Register and ensure these are regularly considered through a North Tyneside lens. For example, risks relating to climate change, cyber security and counter terrorism are incorporated within the Authority’s corporate risks.

1.1.3 Corporate risks are managed at the most senior level in the Authority and are jointly owned by a member of the Senior Leadership Team (SLT) and the Cabinet Member with the relevant portfolio responsibility. Corporate risks are also subject to formal review and challenge by the Senior Leadership Team and Cabinet twice a year. This provides the opportunity, over and above the designated risk owners who are a member of SLT and Cabinet in their own right, to review and challenge corporate risks.

1.1.4 The Authority’s corporate risks were formally considered by the SLT in line with the Authority’s Risk Management Framework on 3 September 2025. This review identified thirteen corporate risks as detailed within the Corporate Risk Management Report appended to this report.

1.2Recommendation(s)

1.2.1 It is recommended that Cabinet:

1. consider and note the corporate risks set out in the Corporate Risk Management Report appended to this report; and

2. if it wishes to amend any of the risks set out in the Corporate Risk Management Report, the Head of Assurance and Risk (Chief Internal Auditor) be advised accordingly and make the necessary changes to the corporate risks.

1.3Forward Plan

Twenty-eight days’ notice of this report has been given, and it first appeared on the Forward Plan published on 29 August 2025.

1.4Council Plan and Policy Framework

1.4.1 The report considers risks relating to all service responsibilities as identified within the Our North Tyneside Plan. 1.4.2 In accordance with the Authority’s Constitution and Budget and Policy Framework Procedure Rules, the Authority has commenced the process to develop a new Council Plan for the period 2025-2029. The new Council Plan will be based on the following five policy priorities: -

1. Working with local people and organisations for a healthier, fairer and better quality of life; 2. Giving our children and young people the best start in life; 3. Building neighbourhoods and town centres that are clean, green and safe, and places to be proud of; 4. Increasing jobs, skills and work experience opportunities; and 5. Delivering more affordable and social housing.

1.4.3 The report considers risks relating to all service responsibilities across these policy priorities.

1.5Information

Background

1.5.1 The Authority has an established risk management process, developed in accordance with national good practice, which is designed to ensure that risks and opportunities relating to the Authority’s business are properly identified, managed and monitored by appropriate risk owners. As part of this process risks are managed at a corporate, strategic and operational level as appropriate and are kept under review on a continuous basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Management Summary ReportReport 49 KB DownloadRead as text
PDF
PUBLIC: Appendix 1 Cabinet Risk Management Report Oct 25 /25Appendix 369 KB Download

At this meeting

Whole meeting

Who was there

9 of 29 attended
MK
Mayor Karen ClarkElected Mayor, present
CJ
Councillor Carl JohnsonDeputy Mayor, present
PE
Councillor Peter EarleyCommittee Member, present
SG
Councillor Sandra GrahamCommittee Member, present
JH
Councillor John HarrisonCommittee Member, present
JH
Councillor Janet HunterCommittee Member, present
HJ
Councillor Hannah JohnsonCommittee Member, present
AM
Councillor Anthony McMullenCommittee Member, apologies
SP
Councillor Steven PhillipsCommittee Member, present
JW
Councillor Joan WalkerCommittee Member, present
DO
Diamond OkoyeGuest, in attendance
DH
David HodgsonGuest, apologies

All 29 on the meeting page

On this subject at North Tyneside

Search all
  1. Corporate Risk Management Summary ReportThis decision
  2. Corporate Risk Management Summary ReportDecided
  3. Carbon Net-Zero 2030 Corporate RiskNoted
  4. Pandemic Flu - Corporate RiskNoted
  5. Health Inequalities - Corporate RiskNoted
  6. Corporate Risk Management Summary ReportNoted

More from North Tyneside Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 North Tyneside Carbon Net-Zero Action Plan Update (2026)Agreeing this decision will support the ongoing delivery of the Authority’s ambitious net-zero programmes and will co... Agreed Open
21 Sep 2026 Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of... Noted Open
21 Sep 2026 North Tyneside Local Plan Publication Draft and SubmissionThe Authority has a statutory duty to prepare and keep up to date a development plan for the strategic development an... Approved Open
21 Sep 2026 No Detriment Financial Support Policy for Kinship Carers Transitioning to Special Guardianship Orders (SGOs)The decision is recommended for the following reasons: · It promotes permanence and stability for children living wit... Decided Open
21 Sep 2026 Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies