AI summaryNorth Tyneside Cabinet approved a £2.453m business case for a new 6-bed children's home for children with complex needs at Benton Lane, Longbenton, projecting annual savings of £1.598m against external care costs.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew 6-bed council-owned children's home at Benton Lane, Longbenton
Money£2.453m capital, £1.598m annual saving50% DfE match funded, plus £0.089m for furnishings
What happens nextBuild starts March 2026Home expected operational by November 2027, subject to planning
Who it affectsChildren in care with complex needsAnd residents near the Benton Lane site in Longbenton
What was decided
Cabinet approved the business case for a 6-bed children's home for children with complex needs at Benton Lane, Longbenton, and authorised the Director of Children's Services to take all necessary steps to deliver it subject to planning approval. Report P11
Cabinet authorised the Director of Children's Services to enter into an agreement with the contracted builder, once planning is granted, and to deal with ancillary matters including Ofsted registration. Report P91
Delegated authority covers consultation with the Cabinet Member for Supporting and Protecting Children, the Director of Resources and the Head of Law.
Why
The council is over-reliant on high-cost external and often out-of-borough placements for children with the most complex needs, with average external costs rising from £5,096 per week in April 2022 to £8,031 per week in July 2025. Report P22, P23, P20
Running the new home is projected to cost £3.336m per year against £4.934m currently spent on equivalent external care for five children, a saving of £1.598m a year and payback within around 1.5 years. Report P12, P13, P112
The project supports the council's aim of keeping children close to home, their families, schools and other services, in line with the Children Act 1989 sufficiency duty and DfE guidance. Report P19, P37, P38
What happens next
Submit the planning application for the six bungalows as a children's home, with a planning decision expected around May 2026, and tender the build contract. Report P178, P181, P186
Begin construction of the six bungalows from March 2026, with practical completion in August 2027 and an Ofsted registration application submitted alongside the build. Report P180, P182, P183
Recruit the registered manager and staff team from September 2027, aiming for the home to be fully operational and occupied from November 2027. Report P183, P102
The money
£2.453m Total capital cost of the six bungalows (50% DfE match funded) Report P11, P110, P121
£1.226m Council match funding for the build (50% of £2.453m) Report P11, P121
£0.089m Cost to furnish the homes, funded by prudential borrowing Report P11, P121, P137, P140
£1.598m Projected annual saving from running the home versus external placements Report P13, P16, P112
£3.336m Projected annual revenue cost of running the home including staffing and borrowing Report P13, P110, P148
£4.934m Current annual cost of external placements for the five in-scope children (September 2025) Report P12, P16
£8,031 per week Average cost of an external children's home placement in July 2025 Report P23
£18,978 per week Average cost of placements for the five most complex in-scope children Report P23, P115
£24,908 per week Most expensive individual external care arrangement Report P23
£17.018m Projected 2025/26 spend on external children's homes against a budget of £11.949m Report P74, P85
Options considered
Chosen: Build the 6-bed children's home at Benton Lane, Longbenton. Site already has planning permission for 36 general needs homes, six of which can be repurposed, and meets DfE grant timescales Report P161, P165, P166
Rejected: If planning for C2 residential use is refused, find an alternative site. No alternative site identified at this stage; would risk DfE grant and project timescales Report P167, P207
Rejected: If the home cannot be used for children's residential care, revert the bungalows to general needs housing in the Housing Revenue Account. Considered a highly unlikely exit strategy given strong and growing demand Report P197, P219
Implications
Financial: Projected £1.598m annual saving depends on the home being occupied by at least five children whose alternative external cost exceeds £12,833 per week; below this tipping point the project ceases to be financially viable. Report P117
Legal: Planning consent is required for the six bungalows to be used as a children's home; any build contract will be approved by the council's legal team and there are no subsidy control issues. Report P186, P210, P211, P212
Legal: The home must be registered with Ofsted under the Children's Homes (England) Regulations 2015 before it can operate. Report P36, P91, P202
Staffing: Proposed staffing of 53 FTEs: one registered manager, one operational manager, three deputy managers and 48 residential care and children's officers, plus a £0.300m non-staffing revenue budget. Report P47, P148, P150
Equalities: The bungalows will be built to M4(3) Cat 3 wheelchair user dwelling standards, supporting access for disabled children. Report P170
Who and where
Children in the council's care with complex needs related to trauma, who are at risk of being deprived of their liberty Report P11, P20, P56, P57
Residents of the wider Benton Lane housing development in Longbenton Report P165, P158
Existing council in-house foster care, children's homes and supported accommodation services, which form a step-down pathway Report P49, P64, P65
Council taxpayers, through potential annual savings of £1.598m and a capital outlay of about £1.226m plus £0.089m for furnishings Report P13, P121
Timeline
December 2025: Business case for the children's home considered at Investment Programme Board Report P178
End of February 2026: Planning application submitted for the children's home Report P178
16 March 2026: Cabinet decision on the business case and start on site for the wider housing development Report P179, P180
May 2026: Target date for planning decision on C2 residential use (8 to 12 weeks) Report P181
August 2027: Practical completion of the six bungalows and Ofsted application submitted Report P182, P183
September 2027: Begin recruitment drive for staffing of the home Report P182
November 2027: Home fully operational and occupied Report P183
Plain English for the jargon
DfE: Department for Education, which is providing 50% match funding for the build.
Ofsted: Office for Standards in Education, the regulator that must register the home before it can operate.
EHCP: Education, Health and Care Plan, the legal document setting out a child's special educational needs support.
HRA: Housing Revenue Account, the ringfenced account holding the council's own housing stock, identified as a fallback use for the bungalows.
C2 / C3 use: Planning use classes: C2 is residential institutions such as children's homes, C3 is general dwelling houses.
JCT Build contract: Standard form of building contract used to manage construction risk with the appointed contractor.
ICB: Integrated Care Board, NHS body that part-funds the HIVE therapeutic team supporting the home.
M4(3) Cat 3: Building regulation standard for wheelchair user dwellings, which the bungalows will meet.
IPB: Investment Programme Board, the council's internal forum that approved the project gateway stages.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB120/25
Resolved
RESOLVED to: (i) Approve the Business Case for a Children’s Home for Children with Complex Needs at Benton Lane, Longbenton at Appendix 1 of the report; (ii) Authorise the Director of Children’s Services in consultation with the Cabinet Member for Supporting and Protecting Children, the Director of Resources and the Head of Law to take all necessary steps to deliver a new 6-bed children’s home for children with complex needs at Benton Lane, Longbenton, subject to the granting of the necessary planning approval and the obtaining of any other necessary requirements to enable the children’s home to be delivered; (iii) Authorise the Director of Children’s Services in consultation with the Director of Resources and the Head of Law, (subject to the granting of the necessary planning approval) to enter into an agreement with the contracted builder to build the children’s home to the Authority’s specifications and to deal with all ancillary matters relating to the delivery of the children’s home, including, but not limited to, obtaining Ofsted registration of the home. Reason for the decision: It allows the necessary steps to be taken by the Authority to deliver on the Authority’s organisational objectives of directly delivering better care for children in its care and of keeping more children who require children’s home care arrangements in the Borough, close to where they call home. The opportunity also has the potential to deliver projected savings of £1.598m per annum to the Authority.
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
Full Business Case November 2025 Contents Page 1. Executive Summary 1
2. Strategic Case 2- 10
3. Objectives 11-13
4. Financial Case 14-17
5. Non-financial Case 18
6. Management Case 19-27
7. Conclusion 28
8. Appendices 29-31
1 1. Executive Summary This business case seeks approval to agree the development of a new Authority owned children’s home for up to 6 children with complex needs which would comprise of three pairs of 2-bed semi-detached bungalows, at the Authority owned site at Benton Lane, Longbenton. The children who would be cared for in this new home currently often end up being cared for out of borough in expensive and sometimes unregistered arrangements, because there are no appropriate registered providers available with homes in our area. This ‘invest to save’ project requires a capital investment of £2.453m including furnishings and fit out of the home and Ofsted registration, with 50% match funding for the build secured from Department for Education (DfE) therefore a total capital investment of £1,226,500 would be required from the Council plus the cost to furnish the homes of £0.089m.
The current cost of external children’s home arrangements per annum, is an average of £0.418m per child. However, the total cost per annum for the five children with needs identified as being in scope for this home, is £4.934m, based on September 2025 care arrangement costs. Although the maximum occupancy is five children, it is anticipated that one bungalow at any one time may be required as single occupancy, therefore the comparable external cost has been based on five children. Whilst it should be noted that it is unlikely to be these specific children who will occupy this home when it is built, they have been used to demonstrate the alternative costs for children with a similar level of need. There is a strongly evidenced need for increased in-house provision for children in care, to avoid over-reliance on external, high-cost children’s home arrangements, which are often also out of borough.
The annual cost of running this bespoke 6-bed Authority owned children’s home, including staffing and borrowing costs, is projected at £3.336m. This represents an annual projected saving of circa £1.598m per financial year. Therefore, it is expected that even allowing for reasonable repairs and inflation of running costs, the initial capital investment would be repaid after 1.5 years (or less if we exclude the DfE funded element and brownfield grant as detailed in the Financial Section of this Business Case). The home would continue to deliver a saving based on current costs for external arrangements, year on year thereafter. This business case seeks approval for the projected budget requirements for the annual running costs of the home and the capital requirement.
To summarise:
1 Current cost per annum Running cost per annum Annual projected of comparable externally for proposed in-house saving/cost avoidance commissioned care development
£4.934m £3.336m £1.598m
2. Strategic Case
2.1The strategic context Our Children in Care Sufficiency Strategy covers policy context, cohort analysis, review of current provision and commissioning intentions in relation to sufficiency of accommodation for children needing social care, in line with our statutory duty (Children Act 1989). This includes a needs assessment and establishes priorities for improving the placement offer.
The overarching strategy in North Tyneside aims to provide appropriate local and in-house care wherever possible, only using external provision in exceptional circumstances.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Public Space Protection OrdersRESOLVED to: (i) Note the consultation exercise undertaken on the proposed extension of The Council of the Borough of...
Strategic Education Review UpdateRESOLVED to: (i) Note the progress made in exploring the potential academisation of Langley First School following th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.