AI summaryNorth Tyneside Audit Committee notes the 2025/26 Internal Audit Plan delivery, with 42 of 49 engagements completed and seven limited assurance opinions issued since November 2025.
Written from the decision and the officer reportPDF Pro
OutcomeNotedPlan performance and audit outcomes received
MoneyNot stated
What happens nextOngoingSeven engagements remain in progress
Who it affectsCouncil governanceAll services subject to internal audit
What was decided
The committee noted performance against the 2025/26 Internal Audit Plan, where 49 revised engagements replaced the original 72, with 42 reports issued and 7 still in progress. Report P2, P20, P22, P26, P39
The committee noted outcomes of internal audit activity completed between November 2025 and July 2026, covering one substantial, twelve reasonable and seven limited assurance opinions, alongside advisory and grant certification work. Report P3, P46, P47
Why
To support Audit Committee in meeting its terms of reference by considering reports from the Chief Internal Auditor on internal audit performance during the year. Report P52
Internal audit resources were reduced in 2025/26 because of long-term absence, jury service, support for the Annual Governance Statement, and providing audit services to another local authority under reciprocal arrangements. Report P18
The Chief Internal Auditor considers the in-year plan changes do not affect the ability to provide an overall annual conclusion and opinion. Report P31
What happens next
Seven engagements remain in progress, including homelessness case management, leasehold service charges, housing rents, payroll, trading standards, health and safety incident reporting and transition. Report P39, P122, P123, P124, P125, P126, P127
The plan will continue to be flexed for changes in resources, the Authority's risk profile, new and emerging risks, delays, grant assurance needs, and ad hoc advisory demand. Report P11, P12, P13, P14, P15, P16, P17
Options considered
Chosen: Note the level of coverage and outcomes as recommended. Supports the Audit Committee in meeting its terms of reference Report P49, P52
Rejected: No other options Report P50
Implications
Financial: No direct financial implications; effective internal audit is part of the Authority's governance and helps reduce the potential for financial loss through fraud, waste and inefficiency. Report P61
Legal: No direct legal implications; the report supports conformance with Global Internal Audit Standards in the UK public sector from 1 April 2025 and the Accounts and Audit Regulations 2015. Report P63, P64
Governance: Internal auditing strengthens the Authority's ability to create, protect and sustain value through independent, risk-based assurance over governance, risk management and controls. Report P5, P6, P7
Risk: No direct risk management implications; the plan is risk-based and the effectiveness of risk management is considered within each assignment. Report P71
Equalities: No equality and diversity implications arising from this report. Report P70
Other: No human rights, crime and disorder, or environment and sustainability implications arising from this report; internal audit is a key strand in counter-fraud arrangements. Report P68, P73, P75
Who and where
The Authority as a whole, with internal audit and Audit Committee having a remit across all priorities of the Our North Tyneside Plan. Report P8
Services receiving limited assurance opinions: Neutral Vendor (Amazon Business), Health and Safety Governance in Highways, Commercial Property, Freedom of Information, Creditors Supplier Database, Actioning Feedback for SEND, and Home Care Payment Arrangements. Report P46, P104, P112, P113, P116, P117, P119, P120
Organisations receiving grants or contracts from the Authority, where internal audit remit extends to them. Report P8
Timeline
May 2025: 2025/26 Internal Audit Plan approved by Audit Committee. Report P10
November 2025: Last update to Audit Committee, the cutoff for this report. Report P42
November 2025 to July 2026: Period covered by the audit outcomes reported at this meeting. Report P3, P42
12 August 2026: Audit Committee meeting where plan performance and outcomes were noted.
Plain English for the jargon
Reasonable Assurance: The system of governance, risk management and internal control is generally sound but matters need addressing to reduce risk to an acceptable level.
Limited Assurance: The system is ineffective, with significant matters needing to be addressed to reduce risks to an acceptable level.
Substantial Assurance: The system is effective in mitigating risks but some improvements are required to reduce risk to an acceptable level.
EzyTreev: Digital system used for tree inspections and risk-based prioritisation.
ContrOCC: System used for recording payments and care records in social care.
CDM: Construction Design and Management regulations.
FRA: Fire Risk Assessment.
EICR: Electrical Installation Condition Report.
UKSPF: UK Shared Prosperity Fund.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC8/26
Resolved
RESOLVED to: i. note the performance against the 2025/2026 Internal Audit Plan as detailed within section 1.4 and Appendix A of the report; and ii. note the outcomes from Internal Audit activity completed between November 2025 and July 2026 as detailed within Appendix B of the report.
Word for word from the decision North Tyneside published for this meeting.Source: democracy.northtyneside.gov.uk
1.2.1 It is recommended that the Audit Committee consider and note:
• performance against the 2025/26 Internal Audit Plan as detailed within section 1.4 of this report and Appendix A, and
• outcomes from Internal Audit activity completed between November 2025 and July 2026 as detailed within Appendix B.
1.3Council plan and policy framework
1.3.1 Internal auditing strengthens the Authority’s ability to create, protect and sustain value by providing the Audit Committee and management with independent, risk-based and objective assurance, advice, insight and foresight.
Page | 1 1.3.2 Internal auditing enhances the Authority’s successful achievement of its objectives, its governance, risk management and control processes, its decision-making and oversight, its reputation and credibility with its stakeholders, and its ability to serve the public interest.
1.3.3 Audit Committee is a key component of the Authority’s governance framework and provides an independent and high-level focus on the adequacy of governance, risk and control arrangements. Its role in ensuring that there is sufficient assurance over these arrangements gives greater confidence to all those charged with governance that those arrangements are effective.
1.3.4 Internal Audit and Audit Committee have a remit across the whole control environment for the Authority. This also extends to organisations to whom the Authority has given grants, contracts and /or partners with and has responsibility as lead or accountable body. As such, Internal Audit and Audit Committee have a remit across all priorities within Our North Tyneside Plan and the policy framework.
1.4Performance against the 2025/26 Internal Audit Plan
1.4.1 The 2025/26 Internal Audit Plan (the Plan) was approved by Audit Committee in May 2025 reflecting the Chief Internal Auditor’s risk assessment at that time and the expected level of resources available to undertake internal audit work across the year.
1.4.2 The Plan is risk based and, inevitably, requires flexibility to enable internal audit to respond to:
• changes in the overall level of resources available to deliver internal audit activity
• changes in the Authority’s risk profile
• consideration of new and emerging risks – advice, insight and foresight to services as they plan for, or implement, new governance, risk management and controls in response to these
• delays in implementing planned changes, new system, new processes or matters are not as complex as first thought – as such planned activity is not required
Page | 2 • satisfy new assurance requirements, e.g. unexpected grant claims, ad hoc investigations etc. Alternatively, there are delays in delivering grant funded activity which defers grant certification requirements into the next financial year
• increased demand for ad hoc advisory services (advice, insight and foresight) to assist services with a range of matters
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
CIPFA FM Code and Resilience reviewRESOLVED to: i. note the outcome of the review of compliance with the CIPFA FM Code and the work required to further ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.