Resolved
RESOLVED UNANIMOUSLY THAT: The application be permitted in accordance with the recommendation of the Director of Services.
Planning Committee decided this item on Tuesday 2 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED UNANIMOUSLY THAT: The application be permitted in accordance with the recommendation of the Director of Services.
PLANNING APPLICATIONS- SECTION A
Installation of a 7.99MWp solar farm and assocaited Report Item No infrastructure. A6
Land To The West Of Gelscoe House Farm Outbuildings Application Reference Gelscoe Lane Diseworth 14/00408/FULM
Applicant: Date Registered [name removed] 6 May 2014
Case Officer: Target Decision Date Sarah Worrall 5 August 2014
Recommendation: PERMIT
Site Location - Plan for indicative purposes only
Reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the controller of Her Majesty’s Stationery Office copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Licence LA 100019329)
Planning Committee 2 September 2014 Development Control Report PLANNING APPLICATIONS- SECTION A
Executive Summary of Proposals and Recommendation
Call In This application has not been called in but is brought to the Planning Committee for consideration due to the proposed development being the first of its kind in the district, and therefore of some public interest, and since it also represents a major development in the countryside and a departure from the development plan.
Proposal
This is a full application for the erection of a 7.99MWp solar farm over a 19.54 ha site. The application information submits that that the site would be split into five parcels and modules would be fixed to arrays that would be arranged in a linear form across the site in rows. The arrays would be laid out west-east to allow the modules to face south and be angled towards the sun at approximately 30 degrees to optimise photovoltaic capture. The proposal would also include the erection of No.7 inverter cabins and No.7 transformer cabins as well as a new substation towards the south eastern boundary. Security fencing and CCTV cameras on 3.1m poles would also be required as part of the scheme. Wildlife corridors and associated landscaping are also proposed as part of the application.
Consultations Members will note that representations from local residents have been made. In terms of those issues raised, all statutory consultees are satisfied that there are no matters that have not been satisfactorily addressed or cannot otherwise be satisfied by way of condition.
Planning Policy
The proposed development would form a renewable energy development in the countryside, but would also represent farm diversification of an existing agricultural operation and would, therefore, be in accordance with the requirements of Countryside Policy S3 of the Adopted Local Plan. Technical reports to address agricultural land classification, heritage assets, landscape and visual impact, highway safety, flood risk and ecological matters have been submitted as part of the application and assessment of these in relation to national and development plan policies is set out in detail in the main report.
Conclusion
The proposed development would have no adverse visual or landscape character or heritage asset impact, and there would be no adverse impact on residential amenities, highway safety or the highway network, site drainage or flora and fauna. As such, the proposed solar farm would be in accordance with national and development plan policies and approval is recommended.
RECOMMENDATION:- PERMIT SUBJECT TO CONDITIONS
Members are advised that the above is a summary of the proposals and key issues contained in the main update report below. Members are advised that this summary should be read in conjunction with the update report below and the original report of October 2013 and the first update report of June 2014 which are attached.
Planning Committee 2 September 2014 Development Control Report PLANNING APPLICATIONS- SECTION A
MAIN REPORT
1.Proposal and Background
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
14/00408/FULM: Installation of a 7.99MWp solar farm and associated infrastructureMinutes | 281 KB | DownloadRead as text |
Follow Planning Committee at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.