Resolved
RESOLVED THAT: The progress against the plan outlined in the Council’s ICT Strategy be noted.
Policy Development Group noted this item on Wednesday 30 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: The progress against the plan outlined in the Council’s ICT Strategy be noted.
NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL
POLICY DEVELOPMENT GROUP – 30 SEPTEMBER 2015
Title of report ICT SERVICE UPDATE
Councillor Nick Rushton 01530 412059 [email protected]
Head of Finance 01530 454520 Contacts [email protected]
ICT Team Manager 01530 454716 [email protected]
To update the Policy Development Group on progress against the Purpose of report medium term plan outlined in the Council’s current ICT strategy.
Council Priorities Value for Money
Implications:
Financial/Staff As indicated in report.
Link to relevant CAT None.
The Corporate Risk Register includes ensuring the Council has Risk Management effective IT Systems and Procedures..
Equalities Impact Screening None.
Human Rights None.
Transformational None. Government
Comments of Head of Paid The report is satisfactory. Service
Comments of Section 151 The report is satisfactory. Officer
Comments of Monitoring The report is satisfactory. Officer
Consultees Corporate Leadership Team (CLT) Background papers ICT Strategy v1.01 Feb 2014
THAT THE COMMITTEE NOTES PROGRESS AGAINST THE Recommendations PLAN OUTLINED IN THE COUNCIL’S ICT STRATEGY
1.0BACKGROUND & PURPOSE
1.1The Council’s current ICT strategy was approved by CLT in March 2014 and covers the period 2014-15 to 2017-18.
1.2The strategy includes a medium term plan designed to bring the Council’s ICT provision in line with standards and technologies deployed within the mainstream of the ICT industry, putting it somewhere ahead of the majority of Councils and public sector organisations that have typically tended to be somewhat behind private sector organisations in the adoption of new technologies.
1.3This report summarises the progress against the medium term plan that has been made since the strategy was approved.
2.0MEDIUM TERM PLAN
2.1The chart below shows the planned broad focus for improvement until 2017/18:
2013/14 2014/15 2015/16 2016/17 2017/18
Infrastructure improvements
Team size reduction
Plan move to cloud
Move to cloud
2.2The key points of the plan were as follows:
The initial focus would be on implementing a number of technical and process improvements identified in a review of the ICT service which had been undertaken by the new ICT Team Manager in October 2013, starting immediately and using existing resources.
The team size would then be reduced progressively as resource demand reduces, using the vacancy review process to avoid the cost and upheaval of redundancy (i.e. the intention was to reduce the team size by not backfilling roles as people leave).
Contracts for the supply of ICT equipment and services would be renewed to co-terminate in 2017/18 to coincide with the expected end of economic life of current investments.
Any large scale move to the cloud delivery model would be planned in 2016/17. There has been some debate in the industry around the security of cloud systems, although concerns have been addressed through various certification programmes and current Central Government guidelines recommend the use of cloud systems. However, time needs to be allowed for CLT to properly understand and consider any risks.
3.0PROGRESS TO DATE
Team Size and Structure
3.1Three members of the ICT team left the Council in September 2014 which presented the opportunity to expedite changes to the size and structure of the ICT team. Following a review of the ICT service a revised structure was put in place on 1 March 2015, with the team now better matched to the needs of the Council and cost savings of £30,000 made in the ICT 2015- 16 budget.
3.2New roles have a greater focus on business skills reflecting the need to closely align the work of the ICT team with operational requirements of front line services. The more technical aspects of the team’s work are now being delivered through service contracts with key suppliers.
3.3Recruiting in to the two new vacant roles has been challenging, but the roles have now been filled. Agency staff have been used to provide cover during the transitional period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ICT StrategyAppendix 1 | 558 KB | Download |
PDF |
ICT Service UpdateMinutes | 170 KB | DownloadRead as text |
Follow Policy Development Group at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Mar 2019 | Tenancy Agreement ChangesRESOLVED THAT: Comments made by the Committee be provided to Cabinet when considering the report. | Decided | Open |
| 6 Mar 2019 | S106 Agreement Contributions to Health - Annual UpdateRESOLVED THAT: The position in terms of Section 106 monies for health be noted. | Noted | Open |
| 6 Mar 2019 | Update on Universal CreditRESOLVED THAT: a) The current position of the Universal Credit roll out be noted. b) The operational impacts on the U... | Noted | Open |
| 6 Mar 2019 | 2018/19 Quarter 3 Performance ReportRESOLVED THAT: a) The report be noted. b) Comments made by the Committee be provided to Cabinet when considering the ... | Noted | Open |
| 6 Mar 2019 | Council Delivery Plan 2019/2020RESOLVED THAT: a) The report be noted. b) Comments made by the Committee be provided to Cabinet when considering the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.