21/00399/FUL: Retrospective change of use of land to industrial (Use Class B2), erection of fencing, engineering works and the installation of an extraction unit, together with the proposed erection of boundary fencing
DecidedPlanning1 paper
Planning Committee decided this item on Tuesday 8 February 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED THAT: The application be permitted in accordance with the recommendation of the Head of Planning and Infrastructure and to include the increase in height of acoustic fencing to the north of the site surrounding the extraction unit. Recorded Vote Title Type Recorded Vote text Result Motion to permit the application in accordance to the officer's recommendation Motion Carried View Recorded Vote for this item
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Retrospective change of use of land to industrial (Use Class Report Item No B2), erection of fencing, engineering works and the A3 installation of an extraction unit, together with the proposed erection of boundary fencing AJ Specialist Welding Rempstone Road Coleorton Coalville Application Reference Leicestershire LE67 8HR 21/00399/FUL
Grid Reference (E) 440111 Date Registered: Grid Reference (N) 318184 5 March 2021 Consultation Expiry: Applicant: 7 January 2022 A J Specialist Welding Ltd 8 Week Date: 30 April 2021 Case Officer: Extension of Time: Karina Duncan 11 February 2022
Recommendation: PERMIT
Site Location - Plan for indicative purposes only
Reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the controller of Her Majesty’s Stationery Office copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Licence LA 100019329)
Planning Committee 8 February 2022 Development Control Report OTHER MATTERS - SECTION B
Executive Summary of Proposals and Recommendation
Call In The application is brought to the Planning Committee as the ward member has requested it be called in on grounds of public concern.
Proposal This is a retrospective application for the change of use of land to industrial (Use Class B2), erection of fencing, engineering works and the installation of an extraction unit, together with the proposed erection of boundary fencing at AJ Specialist Welding, Rempstone Road, Coleorton.
Whilst the application documents include information relating to the proposed changes to the opening hours, the applicant has been advised that a separate application would be required to vary the opening hours on the original planning consent. This application therefore only relates to external alterations to the building to include the provision of an extraction unit, extension to the site to create a car park and alterations to the boundary treatments.
Consultations Members will see from the main report below that 56 letters of objection have been received from third parties, in addition to objections from Coleorton and Worthington Parish Councils. 15 letters of support have been received.
No objections on technical grounds have been raised by other statutory consultees.
Planning Policy The application site lies outside Limits to Development as defined in the adopted North West Leicestershire Local Plan. The site is also located within the National Forest and is located to the south east of the Lount Nature Reserve. The application has been assessed against the relevant paragraphs within the NPPF, the adopted Local Plan and other relevant guidance.
Conclusion The principle of the development is considered to be acceptable and accords with Local Plan Policy S3. The impact upon the character and appearance of the area, together with the associated visual impacts arising from the proposed car park, extraction unit and boundary alterations, would be acceptable subject to the imposition of planning conditions. The application is not considered to result in any unacceptable residential amenity, highway safety, parking, ecology, National Forest, flooding or drainage impacts and on this basis the application also accords with Local Plan Policies IF4, IF7, D2, Cc2, En1 and En3.
It is therefore concluded that the proposed development would comply with the provisions of the development plan as a whole, and the advice set out within the NPPF, subject to the imposition of conditions as recommended within the below report.
The key planning issues arising from the application details are: - Principle of Development; - Residential Amenity and Noise Impacts; - Visual Impacts; - Ecology Impacts, and; - Highway Safety Impacts.
Planning Committee 8 February 2022 Development Control Report OTHER MATTERS - SECTION B
RECOMMENDATION:- PERMIT, SUBJECT TO CONDITIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
21/00399/FUL: Retrospective change of use of land to industrial (Use Class B2), erection of fencing, engineering works and the installation of an extraction unit, together with the proposed erection of boundary fencingMinutes
5721/00399/FUL: Retrospective change of use of land to industrial (Use Class B2), erection of fencing, engineering works and the installation of an extraction unit, together with the proposed erection of boundary fencingThis decision
Who was there
11 of 25 attended
NS
Councillor Nigel SmithChair, present
RB
Councillor Russell BoamDeputy Chair, present
RA
Councillor Robert AshmanSubstitute, present as substitute
DB
Councillor Dave BigbyCommittee Member, present
AB
Councillor Alexander BridgenCommittee Member, apologies, sent representative
DE
Councillor David EverittCommittee Member, present
SG
Councillor Stuart GillardCommittee Member, present
JH
Councillor Jim HoultCommittee Member, present
JL
Councillor John LegrysCommittee Member, present
RM
Councillor Ray MorrisCommittee Member, present
JS
Councillor Jenny SimmonsCommittee Member, present
MW
Councillor Michael WyattCommittee Member, apologies
21/00399/FUL: Retrospective change of use of land to industrial (Use Class B2), erection of fencing, engineering works and the installation of an extraction unit, together with the proposed erection of boundary fencingThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.