Resolved
RESOLVED THAT: The application be permitted in accordance with the recommendation of the Head of Planning and Infrastructure. <caption
Planning Committee decided this item on Tuesday 3 October 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: The application be permitted in accordance with the recommendation of the Head of Planning and Infrastructure. <caption
PLANNING APPLICATIONS- SECTION A
Reserved matters approval (internal access, appearance, Report Item No layout, scale and landscaping) (outline planning permission A2 15/00456/OUTM) for a 45 unit apartment block within the second phase Willow Farm Ashby Road Moira Swadlincote DE12 6DP Application Reference 21/00711/REMM
Grid Reference (E) 432913 Date Registered: Grid Reference (N) 316480 16 April 2021 Consultation Expiry: Applicant: 7 September 2023 MACC Group and Prospect Capital 13 Week Date: 16 July 2021 Case Officer: Extension of Time: Adam Mellor FINAL EXT TO BE AGREED Recommendation: PERMIT
Site Location - Plan for indicative purposes only
Reproduced from Ordnance Survey material with the permission of Ordnance Survey on behalf of the controller of Her Majesty’s Stationery Office copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. Licence LA 100019329)
Planning Committee 3 October 2023 Development Control Report PLANNING APPLICATIONS- SECTION A
Reasons the case is called to the Planning Committee:
This application is brought to Planning Committee originally at the request of Councillor Gill Hoult and subsequently by Councillor Woodman due to the proposal, raising considerable public concern, being outside the defined Limits to Development, differing from the outline permission and that there is no justification for this application to proceed as there are 2, possibly 3, other new care facilities in Ashby.
RECOMMENDATION – PERMIT, subject to the following conditions:
1. Compliance with conditions of outline permission (15/00456/OUTM). 2. Approved plans. 3. Finished floor levels to be delivered in accordance with submitted plans. 4. No raising of land levels unless precise details of finished ground levels are first submitted and approved. 5. Scheme of external materials prior to the care related apartment block being built above damp proof course level to be submitted, approved, and implemented. 6. Design detailing of care related apartment block prior to the care related apartment block being built above damp proof course level to be submitted, approved, and implemented. 7. External meter boxes and rainwater goods to be finished black. 8. Soft landscaping scheme (including timetable for implementation) prior to the care related apartment block being built above damp proof course level to be submitted, approved and implemented. 9. Hard landscaping scheme (including timetable for implementation) prior to the care related apartment block care being built above damp proof course level to be submitted, approved and implemented. 10. Boundary treatment scheme in accordance with submitted plans and removal of permitted development rights for alternative boundary treatment schemes to care home and care related dwellings. 11. Elevational information of boundary treatments prior to boundary treatments being installed to be submitted, approved, and implemented. 12. Details of retaining walls (if required) prior to construction to be submitted, approved and implemented. 13. Scheme of a bin storage point(s) (including timetable for implementation) prior to the care related apartment block being built above damp proof course level to be submitted, approved and implemented. 14. Timetable for the delivery of the pedestrian link to National Forest woodland prior to first occupation to be submitted, approved, and implemented. 15. Signage for the pedestrian link to National Forest woodland prior to first occupation to be submitted, approved, and implemented. 16. Delivery of access arrangements (including visibility splays) in accordance with submitted plans prior to first occupation. 17. Delivery of off-street parking and turning arrangements in accordance with submitted plans prior to first occupation. 18. Delivery of secure cycle parking facilities prior to the first use of the development to be submitted, approved, and implemented.
1. Proposals and Background
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A2: 21/00711/REMM: Reserved matters approval (internal access, appearance, layout, scale and landscaping) (outline planning permission 15/00456/OUTM) for a 45 unit apartment block within the second phaseMinutes | 3.5 MB | DownloadRead as text |
Follow Planning Committee at North West Leicestershire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.